Permit: T22CM01026
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1010 N ANITA AV 01
Address NEW:
1010 N ANITA AV 01
Apply Date:
02/10/2022
Applicant:
Cyrus Moore
Description:
LOT A - building 3 duplexes on 3 different lots at 1010 N. anita, 1006 N. Anita and 1011 N. Van Alst
Permit Reviews
Permit Number - T22CM01026
Permit Status: Issued
Permit Description: LOT A - building 3 duplexes on 3 different lots at 1010 N. anita, 1006 N. Anita and 1011 N. Van Alst
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2022 | 3RD PARTY REVIEW - RESIDENTIAL | 05/26/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM01026
Permit Status: Issued
Permit Description: LOT A - building 3 duplexes on 3 different lots at 1010 N. anita, 1006 N. Anita and 1011 N. Van Alst
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 06/03/2024 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. |
| 06/03/2024 | Post-Installed Anchor Inspection Report is required. |
| 06/03/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM01026
Permite Description: LOT A - building 3 duplexes on 3 different lots at 1010 N. anita, 1006 N. Anita and 1011 N. Van Alst
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2023 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 10/31/23: missing water hammer arrestor at dishwasher, gfci receptacle missing under sink, panel scheduled missing, prop secure whip at A/C unit, properly secure disconnect stand to roof at A/C unit, A/C condensate drain needs to be coated for up rays and be properly supported. Water heater pressure relief not terminated. |
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
| 12/12/2023 | BULD - Electrical Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM01026
Permit Description: LOT A - building 3 duplexes on 3 different lots at 1010 N. anita, 1006 N. Anita and 1011 N. Van Alst
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/29/2022 | COT - RSPL - Sewer | Passed | {Activity date: 07/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved connected to HCS} | |
| 07/29/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
| 08/10/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved for dual meter location} ; {Activity date: 08/08/2022; Status: Cancelled; Inspector: DQUINN; Comment: Entered by VVERA1 - ca Per Cyrus } |
|
| 08/10/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/08/2022; Status: Cancelled; Inspector: DQUINN; Comment: Entered by VVERA1 - ca Per Cyrus } |
|
| 09/01/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to dry in roof system.} | |
| 09/07/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to install intermediates.} | |
| 10/19/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to drop water test in bath tubs.} | |
| 10/19/2022 | RSEL - Electrical Progress | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to insulate and cover walls.} | |
| 10/19/2022 | RSME - Mechanical Progress | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/19/2022 | COT - RSBU - Sustainability | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 02/01/2023 | COT - RSEL - Electrical Underground | Passed | Approved for underground electric conduit from dual pack meter location to unit 1 and unit 2 sub-panels, okay to backfill progress areas | |
| 11/09/2023 | RSBU - Building Final | Passed | Approved units #1 and #2, all items were addressed | |
| 11/09/2023 | COT - RSEL - Service Upgrade | Passed | Approved units #1 and #2 | |
| 11/09/2023 | COT - RSME - Mechanical Final | Passed | Approved units #1 and #2, all items were addressed | |
| 11/09/2023 | COT - RSEL - Electrical Final | Passed | Approved units #1 and #2, all items were addressed |