Permit: T22CM01018
Permit Details
Apply Date:
02/10/2022
Applicant:
David Perreira
Description:
Conversion of gray shell into coffee cafe
Permit Reviews
Permit Number - T22CM01018
Permit Status: Complete
Permit Description: Conversion of gray shell into coffee cafe
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/10/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/06/2022 | COMPLETED |
03/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/10/2023 | APPROVED |
03/15/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/21/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM01018
Permit Status: Complete
Permit Description: Conversion of gray shell into coffee cafe
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
05/06/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
05/06/2022 | SHOP DRAWINGS REQUIRED FOR AUTOMATIC FIRE SPRINKLERS. |
05/06/2022 | SHOP DRAWINGS REQUIRED FOR KITCHEN HOOD SUPPRESSION SYSTEM. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01018
Permite Description: Conversion of gray shell into coffee cafe
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
11/16/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | |
10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
02/22/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Complete inspections. Ok to make application for Temporary Certificate of Occupancy. |
02/28/2023 | COT - LCME - Mechanical Final | N/A | Not Ready | |
03/07/2023 | COT - LCME - Kitchen Hood | N/A | Canceled | Cancel inspection, already approved |
02/28/2023 | COT - LCPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01018
Permit Description: Conversion of gray shell into coffee cafe
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/26/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 05/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. Ok to cover progress areas} | |
06/20/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. Please add this inspection to the permit. Ok to cover progress areas.} | |
11/16/2022 | COT - LCBU - Preslab | Passed | ||
11/16/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
11/16/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
11/16/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
11/16/2022 | COT - LCBU - Framing | Passed | ||
02/17/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
02/17/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
02/17/2023 | COT - LCME - Mechanical Above Ceiling | Passed | all mechanical equipment and ductwork is installed. | |
02/17/2023 | COT - LCBU - Building Above Ceiling | Passed | all mechanical, electrical,and plumbing is complete. | |
02/17/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
02/17/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
02/21/2023 | COT - FCON - Sprinkler - Final | Passed | ||
02/22/2023 | COT - LCEL - Electrical Final | Passed | ||
03/07/2023 | COT - FCON - Alarm - Final | Passed | ||
03/07/2023 | COT - FCON - Fire - Final | Passed | ||
03/07/2023 | COT - FCON - Hood System - Final | Passed | ||
03/27/2023 | COT - LCBU - Building Final | Passed | ||
03/27/2023 | COT - LCME - Mechanical Final | Passed | ||
03/27/2023 | COT - LCME - Kitchen Hood | Passed | ||
03/27/2023 | COT - LCPL - Plumbing Final | Passed |