Permit: T22CM00904
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1923 N FORGEUS AV
Address NEW:
1923 N FORGEUS AV
Apply Date:
02/07/2022
Applicant:
Melinda Preston
Description:
R-Renovate BR & Laundry and Storage into Master Bath
Outstanding Activity Conditions
Permit Number - T22CM00904
Permit Status: Complete
Permit Description: R-Renovate BR & Laundry and Storage into Master Bath
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00904
Permite Description: R-Renovate BR & Laundry and Storage into Master Bath
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2022 | COT - RSPL - Sewer | N/A | Canceled | {Activity date: 09/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/02/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VVERA1 - N/A} |
| 09/02/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Canceled | {Activity date: 09/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/02/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VVERA1 - N/A} |
| 12/14/2022 | COT - RSBU - Roof Nailing | N/A | Not Applicable | |
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00904
Permit Description: R-Renovate BR & Laundry and Storage into Master Bath
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/02/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 10/13/2022 | COT - RSBU - Preslab | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by ESTEVEN1 - 3015 Plumbing pre-slab approved} | |
| 12/14/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 12/14/2022 | COT - RSPL - Gas Pressure Test | Passed | no clearance needed. | |
| 12/14/2022 | RSME - Mechanical Progress | Passed | intermediate. | |
| 12/14/2022 | COT - LCBU - Framing | Passed | ||
| 02/16/2023 | COT - BULD - SWG Clearance | Passed | ||
| 02/16/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 02/16/2023 | COT - RSME - Mechanical Final | Passed | ||
| 02/16/2023 | RSBU - Building Final | Passed | ||
| 02/16/2023 | COT - RSEL - Electrical Final | Passed | ||
| 02/16/2023 | COT - RSEL - Outdoor Lighting | Passed |