Permit: T22CM00893
Permit Details
Apply Date:
02/04/2022
Applicant:
Technicians for Sustainability
Description:
roof mount 5.60 kW photovoltaic solar system; 14 AC modules, 2 branches, PV subpanel, 30A PV breaker on 200A bus with 200A MCB
Contractors:
- Technicians for Sustainability
Permit Reviews
Permit Number - T22CM00893
Permit Status: Final
Permit Description: roof mount 5.60 kW photovoltaic solar system; 14 AC modules, 2 branches, PV subpanel, 30A PV breaker on 200A bus with 200A MCB
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/04/2022 | OTHER | 03/18/2022 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T22CM00893
Permit Description: roof mount 5.60 kW photovoltaic solar system; 14 AC modules, 2 branches, PV subpanel, 30A PV breaker on 200A bus with 200A MCB
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/09/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE DGC |
| 05/09/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap Clear dgc Close permit |
| 05/09/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |