Permit: T22CM00804
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
761 W PRESIDENT ST
Address NEW:
761 W PRESIDENT ST
Apply Date:
02/02/2022
Applicant:
Eriberto Gamino
Description:
SFR
Permit Reviews
Permit Number - T22CM00804
Permit Status: Complete
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/21/2022 | COMPLETED |
| 03/24/2022 | RESUBMITTAL | 03/25/2022 | COMPLETED |
| 04/11/2023 | RESIDENTIAL NEW DWELLING v.1 | 05/09/2023 | APPROVED |
| 03/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/28/2025 | APPROVED |
Conditions
Permit Number - T22CM00804
Permit Status: Complete
Permit Description: SFR
| Date | Description | Comments |
|---|---|---|
| 10/02/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as a contact. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 01/07/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00804
Permite Description: SFR
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Roof Nailing | N/A | Not Ready | |
| 05/15/2023 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | Canceled per homeowner. 5/15/2023 |
| 05/15/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Canceled | Canceled per homeowner. 5/15/2023 |
| 12/07/2022 | COT - LCBU - Framing | N/A | Partial Pass | partial per intermediates. |
| 10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
| 10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 10/26/2022 | COT - RSEL - Electrical Underground | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00804
Permit Description: SFR
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/20/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved 1” building to meter, okay to backfill progress areas} ; {Activity date: 05/19/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR} | |
| 05/20/2022 | COT - RSPL - Sewer | Passed | {Activity date: 05/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved connected to existing main, okay to backfill progress areas} ; {Activity date: 05/19/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR} | |
| 05/20/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 05/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/19/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR, not on test} | |
| 05/26/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/26/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 05/26/2022 | COT - RSBU - Preslab | Passed | {Activity date: 05/26/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 05/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/26/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 12/07/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 12/07/2022 | COT - RSBU - Roof Nailing | Passed | ||
| 05/23/2023 | COT - LCPL - Plumbing Intermediate | Passed | Approved 5/23/2023 | |
| 05/23/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Approved 5/23/2023 | |
| 05/23/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
| 05/23/2023 | COT - LCBU - Framing | Passed | ||
| 05/23/2023 | COT - RSEL - Construction Power | Passed | Clearance for TEP ECO. 5/23/2023 | |
| 05/23/2023 | RSME - Mechanical Progress | Passed | ||
| 12/05/2023 | BULD - Electrical Clearance | Passed | TEP INCR | |
| 11/06/2024 | RSBU - Building Final | Passed | ||
| 11/06/2024 | COT - RSEL - Electrical Final | Passed | ||
| 11/06/2024 | COT - RSME - Mechanical Final | Passed | ||
| 11/06/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 11/06/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 11/06/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 11/06/2024 | COT - BULD - SWG Clearance | Passed | N/a. Gas meter is in place. 11/6/2024 |