Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM00774
Permit Details
Apply Date:
02/01/2022
Applicant:
Andrea Flood
Description:
SFR F50A19 T19-M0034
Permit Reviews
Permit Number - T22CM00774
Permit Status: Issued
Permit Description: SFR F50A19 T19-M0034
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/03/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM00774
Permit Status: Issued
Permit Description: SFR F50A19 T19-M0034
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
02/01/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
02/01/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 ISACCEPTED AND RELEASED BY PCRWRD |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM00774
Permit Description: SFR F50A19 T19-M0034
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/16/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/16/2022 | COT - RSPL - Sewer | Passed | {Activity date: 03/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/16/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/25/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/25/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
03/25/2022 | COT - RSBU - Preslab | Passed | {Activity date: 03/25/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
03/25/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/25/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
03/25/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/25/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
05/12/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 05/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
11/07/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/07/2022 | COT - RSEL - Construction Power | Passed | clearance required. TEP ECO | |
11/15/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
11/15/2022 | COT - LCBU - Framing | Passed | ||
12/01/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
02/01/2023 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
03/03/2023 | COT - RSPL - Plumbing Final | Passed | ||
03/03/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
03/03/2023 | COT - RSEL - Electrical Final | Passed | ||
03/03/2023 | RSBU - Building Final | Passed | ||
03/03/2023 | COT - RSME - Mechanical Final | Passed |