Permit: T22CM00725
Permit Details
Apply Date:
01/31/2022
Applicant:
Thinh Le
Description:
NAIL SALON
Permit Reviews
Permit Number - T22CM00725
Permit Status: Issued
Permit Description: NAIL SALON
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/31/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/03/2022 | COMPLETED |
10/07/2022 | REVISION - - 1ST | 10/13/2022 | COMPLETED |
Conditions
Permit Number - T22CM00725
Permit Status: Issued
Permit Description: NAIL SALON
Date | Description | Comments |
---|---|---|
05/03/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
09/28/2022 | WATER DISINFECTION REPORT REQUIRED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM00725
Permite Description: NAIL SALON
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM00725
Permit Description: NAIL SALON
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/13/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
06/16/2022 | COT - LCBU - Preslab | Passed | {Activity date: 06/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
07/01/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 07/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
07/26/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
07/26/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved Ok to insulate and cover walls. } |
|
07/26/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
07/26/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
07/26/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
08/09/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, all exposed} | |
08/09/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 07/01/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA all except Plumbing areas.} | |
08/09/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
09/08/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 09/08/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
09/08/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 09/08/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } | |
09/28/2022 | COT - LCPL - Plumbing Final | Passed | {Activity date: 09/28/2022; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF WATER DISINFECTION REPORT COMPLETED} ; {Activity date: 09/08/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Partial Approval pending chlorination report approval.} |