Apply Date:
01/31/2022
Applicant:
Celina Rodriguez
Description:
SFR KBME1609 T21-M0008

Outstanding Activity Conditions

Permit Number - T22CM00719
Permit Status: Issued
Permit Description: SFR KBME1609 T21-M0008
Total Outstanding Activity Conditions - 4
Date Name
01/31/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
01/31/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
01/31/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
01/31/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM00719
Permite Description: SFR KBME1609 T21-M0008
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSEL - Construction Power N/A Not Ready
10/26/2022 COT - RSPL - Yard Water Line N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM00719
Permit Description: SFR KBME1609 T21-M0008
Total Completed Inspections - 21
Date Description Inspector Results Comments
02/15/2022 COT - RSPL - Sewer Passed {Activity date: 02/15/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved}
02/15/2022 COT - RSPL - Rough Soil Passed {Activity date: 02/15/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved}
03/15/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 03/15/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/08/2022; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Not ready}
03/15/2022 COT - RSBU - Preslab Passed {Activity date: 03/15/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/08/2022; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Not ready}
03/15/2022 COT - RSEL - Electrical Underground Passed {Activity date: 03/15/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
03/15/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/15/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/08/2022; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Not ready}
06/29/2022 COT - RSBU - Roof Nailing Passed {Activity date: 06/29/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved}
06/29/2022 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 06/29/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved}
08/17/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 08/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
08/17/2022 COT - LCBU - Framing Passed {Activity date: 08/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
09/20/2022 RSME - Mechanical Progress Passed {Activity date: 09/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/25/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor

} ; {Activity date: 08/17/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready block condensate at floor

}
09/20/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 09/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/25/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor

} ; {Activity date: 08/17/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - not ready, no pressure
}
09/21/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 09/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/20/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. DWV is not under test. Another failed inspection will result in a re-inspection fee.} ; {Activity date: 08/25/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor

} ; {Activity date: 08/17/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready upstairs closet needs nail stop and fur out, Need nail stops on top and bottom plates, no water on DWV}
12/12/2022 BULD - Electrical Clearance Passed
12/15/2022 COT - BULD - SWG Clearance Passed clearance for Southwest Gas.
12/22/2022 COT - RSPL - Yard Water Line Passed
12/22/2022 COT - RSPL - Plumbing Final Passed
12/22/2022 COT - RSEL - Outdoor Lighting Passed
12/28/2022 COT - RSEL - Electrical Final Passed
12/28/2022 RSBU - Building Final Passed
12/28/2022 COT - RSME - Mechanical Final Passed

Scheduled Inspections

Scheduled Inspections - T22CM00719
Status: Issued
Description: SFR KBME1609 T21-M0008
Scheduled Date Description Entered By Entered Date
COT - RSEL - Construction Power Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SITE PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW