Permit: T22CM00688
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1424 N RICHEY BL 1
Address NEW:
1424 N RICHEY BL 1
Apply Date:
01/28/2022
Applicant:
Description:
DPLX SWC2152 T21-M0059
Outstanding Activity Conditions
Permit Number - T22CM00688
Permit Status: Issued
Permit Description: DPLX SWC2152 T21-M0059
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 01/28/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
| 02/23/2022 | FUP T22OT00120 MUST BE PAID BEFORE FINAL INSPECTIONS. |
| 04/25/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm |
| 04/25/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Conditions
Permit Number - T22CM00688
Permit Status: Issued
Permit Description: DPLX SWC2152 T21-M0059
| Date | Description | Comments |
|---|---|---|
| 02/23/2022 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. | |
| 02/23/2022 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. | |
| 02/23/2022 | FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM00688
Permit Description: DPLX SWC2152 T21-M0059
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 06/28/2022 | COT - RSBU - Preslab | Passed | {Activity date: 06/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 06/28/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 07/07/2022 | COT - RSPL - Sewer | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/05/2022; Status: Cancelled; Inspector: DQUINN; Comment: Entered by NGARCIA3 - ca Per Eric} |
|
| 07/15/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/05/2022; Status: Cancelled; Inspector: DQUINN; Comment: Entered by NGARCIA3 - ca} | |
| 08/05/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/28/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CA per call from contractor.} ; {Activity date: 07/25/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready prior to contractor} | |
| 08/05/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 08/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/25/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready prior to contractor} | |
| 08/31/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/26/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Denied:1-Breakers must be accessible to all occupants( not behind locked door of bedroom). 2-Ufer connection is not accessible.} ; {Activity date: 08/25/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor } |
|
| 09/02/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/25/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready prior to contractor} | |
| 09/02/2022 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/05/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval several pin holes in joints and not sealed behind top plate and top of wall on first layer} ; {Activity date: 07/25/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready prior to contractor} | |
| 10/10/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - CODE ECO/UNITS #1, #2} | |
| 10/10/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap Clear eco for #1 #2} |
|
| 01/09/2023 | COT - LCBU - Framing | Passed | ||
| 01/09/2023 | COT - RSEL - Electrical Final | Passed | ||
| 01/09/2023 | COT - RSEL - Outdoor Lighting | Passed | front & rear porch light fixtures are working | |
| 01/09/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 01/09/2023 | COT - RSME - Mechanical Final | Passed | ||
| 01/09/2023 | RSBU - Building Final | Passed | project is complete | |
| 01/09/2023 | COT - RSEL - Electrical Underground | Passed | ||
| 01/09/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 01/09/2023 | RSME - Mechanical Progress | Passed |