Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM00666
Permit Details
Apply Date:
01/28/2022
Applicant:
Description:
THIS PROJECT CONSISTS OF THE CONSTRUCTION OF A NEW 14,644 S.F. GROUND-UP STRUCTURE TO HOUSE A MEDICAL
Permit Reviews
Permit Number - T22CM00666
Permit Status: Complete
Permit Description: THIS PROJECT CONSISTS OF THE CONSTRUCTION OF A NEW 14,644 S.F. GROUND-UP STRUCTURE TO HOUSE A MEDICAL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/28/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 03/03/2022 | COMPLETED |
03/10/2022 | RESUBMITTAL | 04/08/2022 | COMPLETED |
04/08/2022 | RESUBMITTAL | 08/05/2022 | COMPLETED |
09/16/2022 | RESUBMITTAL | 09/20/2022 | COMPLETED |
07/11/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/12/2023 | APPROVED |
08/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/02/2023 | APPROVED |
04/13/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/13/2023 | REQUIRES RESUBMIT |
10/16/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/26/2023 | APPROVED |
06/20/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/28/2023 | APPROVED |
Conditions
Permit Number - T22CM00666
Permit Status: Complete
Permit Description: THIS PROJECT CONSISTS OF THE CONSTRUCTION OF A NEW 14,644 S.F. GROUND-UP STRUCTURE TO HOUSE A MEDICAL
Date | Description | Comments |
---|---|---|
04/11/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
04/11/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
09/20/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required | |
09/20/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE | |
10/05/2022 | BIO-LIFE PLASMA SERVICES - ISSUED WITH TYPE III SEWER CAPACITY WAIVER #P22WC00114 DATED 4/8/22 - CONNECTING TO NEW 1-1/2" WATER METER PER PLUMBING DRAWINGS - CONNECTING TO RELOCATED ON-SITE PRIVATE SEWER - NOTE: “No Final and No Certificate of Occupancy to be issued for COT building Permit #T22CM00666 until the Construction Authorization and the Discharge Authorization is issued by PDEQ for the relocation of a portion of the existing on-site private sewer #PV-2002-014 with private manholes, per DP22-0066”. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00666
Permite Description: THIS PROJECT CONSISTS OF THE CONSTRUCTION OF A NEW 14,644 S.F. GROUND-UP STRUCTURE TO HOUSE A MEDICAL
Total Outstanding Inspections - 23
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
10/26/2022 | COT - FCON - Underground Flush | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
10/26/2022 | COT - FCON - Underground Pressure | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
11/08/2022 | COT - LCPL - Sewer | N/A | Partial Pass | partial approval for three manholes and connecting pipe pressure and mandrel pull |
10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
05/01/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
04/24/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | 4-24-23: Exterior walls. |
05/24/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | partial approval for duct sealing in all but exam rooms |
05/09/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | In wall waste and vent, domestic water lines in walls under hydro test at West half of building. Ok to cover progress areas. |
04/24/2023 | COT - LCBU - Framing | N/A | Partial Pass | |
06/05/2023 | COT - LCEL - Electrical Progress | N/A | Partial Pass | for grounding in sub panels |
FCON – OH Piping & Hydro | N/A | Not Ready | Contractor called in the wrong inspection | |
05/05/2023 | COT - LCBU - Building Progress | N/A | Partial Pass | 5-5-23: Drywall nailing for all except restrooms. |
07/03/2023 | COT - LCPL - Backwater Valve | N/A | Not Ready | |
07/11/2023 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
07/17/2023 | COT - LCME - Mechanical Final | N/A | Not Ready | |
07/17/2023 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
07/17/2023 | COT - LCEL - Electrical Final | N/A | Not Ready | |
07/17/2023 | COT - LCBU - Building Final | N/A | Partial Pass | recommend for level 2 TCO |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00666
Permit Description: THIS PROJECT CONSISTS OF THE CONSTRUCTION OF A NEW 14,644 S.F. GROUND-UP STRUCTURE TO HOUSE A MEDICAL
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - CODE INCR} | |
10/19/2022 | COT - LCEL - Temporary Service | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved ok for clearance INCR } ; {Activity date: 10/12/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} |
|
12/20/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
02/02/2023 | COT - LCPL - Rough Soil | Passed | ||
02/08/2023 | COT - LCPL - Plumbing Progress | Passed | Yard water line. | |
02/22/2023 | COT - LCBU - Preslab | Passed | ||
04/07/2023 | COT - LCBU - Roof Nailing | Passed | see third party insp | |
04/18/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
05/02/2023 | COT - LCEL - Electrical Intermediate | Passed | Ok to cover walls; except for plumbing areas. | |
05/30/2023 | BULD - Electrical Clearance | Passed | Approved 1200A service entrance from existing transformer, ECO Clearance to TEP is required | |
05/31/2023 | COT - LCBU - Framing | Passed | ||
07/11/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
07/11/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
07/11/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
07/13/2023 | COT - FCON - Sprinkler - Final | Passed | ||
07/13/2023 | COT - FCON - Fire - Final | Passed | ||
07/13/2023 | COT - FCON - Alarm - Final | Passed | ||
07/14/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
08/01/2023 | COT - LCBU - Building Final | Passed | ||
08/03/2023 | ENGR Engineering Final | Passed | ok fo Level 4 for TCO for Occupency |