Permit: T22CM00665
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
9748 E CRYSTAL POINT TR
Address NEW:
9748 E CRYSTAL POINT TR
Apply Date:
01/28/2022
Applicant:
Andrea Flood
Description:
SFR F50A19 T19-M0034
Outstanding Activity Conditions
Permit Number - T22CM00665
Permit Status: Issued
Permit Description: SFR F50A19 T19-M0034
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 01/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 01/28/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 ISACCEPTED AND RELEASED BY PCRWRD |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM00665
Permit Description: SFR F50A19 T19-M0034
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/15/2022 | COT - RSPL - Sewer | Passed | {Activity date: 03/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/14/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor} | |
| 03/15/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/14/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor} | |
| 03/24/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 03/24/2022 | COT - RSBU - Preslab | Passed | {Activity date: 03/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 03/24/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 03/24/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 05/05/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 05/05/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 11/04/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 11/04/2022 | COT - LCBU - Framing | Passed | ||
| 11/04/2022 | COT - RSEL - Construction Power | Passed | clearance required. TEP ECO | |
| 11/23/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 02/03/2023 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 02/14/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 02/14/2023 | COT - RSEL - Electrical Final | Passed | ||
| 02/14/2023 | RSBU - Building Final | Passed | ||
| 02/14/2023 | COT - RSME - Mechanical Final | Passed | ||
| 02/14/2023 | COT - RSEL - Outdoor Lighting | Passed |