Permit: T22CM00646
Permit Details
Apply Date:
01/27/2022
Applicant:
Anthony Vidal
Description:
SFR
Permit Reviews
Permit Number - T22CM00646
Permit Status: Issued
Permit Description: SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/27/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 02/17/2022 | COMPLETED |
05/05/2022 | RESUBMITTAL | 05/10/2022 | COMPLETED |
05/24/2022 | RESUBMITTAL | 05/25/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM00646
Permit Status: Issued
Permit Description: SFR
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
05/25/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm |
05/25/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM00646
Permite Description: SFR
Total Outstanding Inspections - 12
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/09/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 05/09/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
05/09/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 05/09/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
10/26/2022 | COT - RSEL - Electrical Underground | N/A | Not Ready | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - RSPL - Sewer | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
02/15/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Canceled | canceled per contractor |
10/28/2024 | COT - RSPL - Yard Water Line | N/A | Re-inspection required | Arrived on site 10/28/24, no access through gate. Called Anthony Vidal Phone: 520-248-7975and left voicemail, no response received. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM00646
Permit Description: SFR
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/07/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
07/13/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 07/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
07/13/2022 | COT - RSBU - Preslab | Passed | {Activity date: 07/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
07/13/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
07/26/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
07/26/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
08/17/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - CODE ECO} | |
08/17/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap Clear eco} |
|
03/02/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Ok to insulate and cover walls. |