Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
01/26/2022
Applicant:
Description:
SFR

Permit Reviews

Permit Number - T22CM00597
Permit Status: Issued
Permit Description: SFR
Start Date Submittal Complete Date Status  
01/26/2022 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 03/09/2022 COMPLETED Review Details
04/26/2022 RESUBMITTAL 06/02/2022 COMPLETED Review Details
06/09/2022 RESUBMITTAL 07/22/2022 COMPLETED Review Details

Conditions

Permit Number - T22CM00597
Permit Status: Issued
Permit Description: SFR
Date Description Comments
02/16/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
02/16/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/22/2022 This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm
07/22/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM00597
Permite Description: SFR
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
05/03/2022 COT - LCPL - Plumbing Intermediate N/A Canceled {Activity date: 05/03/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - }
05/03/2022 RSME - Mechanical Progress N/A Canceled {Activity date: 05/03/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - }
10/26/2022 COT - RSPL - Yard Water Line N/A Not Ready
10/26/2022 COT - RSEL - Construction Power N/A Not Ready
10/27/2022 COT - LCBU - Framing N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM00597
Permit Description: SFR
Total Completed Inspections - 21
Date Description Inspector Results Comments
08/04/2022 COT - RSPL - Rough Soil Passed {Activity date: 08/04/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to cover}
08/23/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 08/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
08/23/2022 COT - RSBU - Preslab Passed {Activity date: 08/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
08/23/2022 COT - RSEL - Electrical Underground Passed {Activity date: 08/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
08/23/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 08/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, special inspection reqd. for PT foundation}
09/23/2022 COT - RSBU - Roof Nailing Passed {Activity date: 09/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to dry in roof system. Please cancel this inspection for 26 September.}
09/23/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 09/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to cover exterior walls}
12/06/2022 COT - RSEL - Construction Power Passed
12/15/2022 COT - RSPL - Sewer Passed Approved with necessary 500gallon tank and sanitary pump to HCS, okay to backfill progress areas
12/19/2022 COT - LCBU - Framing Passed
12/20/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed corrections were made
01/09/2023 COT - HCBU - Interior Shear Bracing Passed corrections were made
03/29/2023 COT - RSPL - Gas Pressure Test Passed This inspection was for a gas pressure test FINAL. Please clear gas with SWG.
04/05/2023 COT - RSEL - Outdoor Lighting Passed
04/05/2023 COT - RSPL - Plumbing Final Passed All plumbing fixtures are installed and operational.
04/05/2023 COT - FCON - Sprinkler - Final Passed
04/05/2023 COT - RSME - Mechanical Final Passed A/c equipment is installed and operational. Registers are installed in every room.
04/05/2023 FCON – OH Piping & Hydro Passed
04/05/2023 RSBU - Building Final Passed Building is complete. Okay to issue a Level 4 Certificate of Occupancy.
04/05/2023 COT - FCON - Fire - Final Passed
04/05/2023 COT - RSEL - Electrical Final Passed All required GFCI outlets are operating properly. Bedrooms are equipped with an AFCI breaker at the panel. Electrical panel is properly labeled.

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
COT LETTER OF INTENT AND SIGNED PERMIT.PDF DOCUMENTS VIEW
HVAC CALCS.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
POST TENSION CALCS.PDF DOCUMENTS VIEW
SOILS REPORT.PDF DOCUMENTS VIEW
TRUSS CALCS.PDF DOCUMENTS VIEW
TRUSS LAYOUT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
HVAC CALCS.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
LETTER OF INTENT.PDF DOCUMENTS VIEW
SOILS REPORT.PDF DOCUMENTS VIEW
POST TENSION CALCS.PDF DOCUMENTS VIEW
TRUSS LAYOUT.PDF DOCUMENTS VIEW
TRUSS CALCS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW