Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM00575
Permit Details
Apply Date:
01/25/2022
Applicant:
Alexander Anderson
Description:
SFR MPLAN1510 T20-M0040
Permit Reviews
Permit Number - T22CM00575
Permit Status: Complete
Permit Description: SFR MPLAN1510 T20-M0040
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/25/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 02/16/2022 | COMPLETED |
06/29/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/07/2023 | APPROVED |
07/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/24/2023 | APPROVED |
Conditions
Permit Number - T22CM00575
Permit Status: Complete
Permit Description: SFR MPLAN1510 T20-M0040
Date | Description | Comments |
---|---|---|
01/25/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
01/25/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
01/25/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
01/25/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
01/25/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
02/16/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
01/25/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00575
Permite Description: SFR MPLAN1510 T20-M0040
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
10/26/2022 | COT - RSBU - Roof Nailing | N/A | Not Ready | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00575
Permit Description: SFR MPLAN1510 T20-M0040
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/14/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to backfill} | |
04/14/2022 | COT - RSPL - Sewer | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to backfill} | |
04/14/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
05/09/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
05/16/2022 | COT - RSBU - Preslab | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} ; {Activity date: 05/09/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Under house only, no garage. } |
|
05/16/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap Note: approved ufer is in garage footing, and approved under slab conduit is to house island} |
|
05/16/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} ; {Activity date: 05/09/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Under house only, no garage. } |
|
08/17/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to cover exterior walls.} | |
09/13/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/13/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to insulate and cover walls } |
|
09/13/2022 | RSME - Mechanical Progress | Passed | {Activity date: 09/13/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
09/14/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to insulate and cover walls.} ; {Activity date: 09/13/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Electric only.} | |
09/14/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE TMPP} | |
09/14/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/13/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Waste lines are not under hydro test.} | |
09/14/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 09/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved CLEARANCE: Code: TMPP. Ok to set for construction power. } ; {Activity date: 09/13/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Gas line is not under pressure test.} |
|
10/19/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
11/29/2022 | COT - RSEL - Construction Power | Passed | ||
05/31/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
05/31/2023 | COT - RSBU - Roof Nailing | Passed | ||
05/31/2023 | COT - RSEL - Electrical Final | Passed | ||
05/31/2023 | COT - RSME - Mechanical Final | Passed | ||
08/04/2023 | COT - RSPL - Plumbing Final | Passed | ||
08/08/2023 | RSBU - Building Final | Passed | Approved. 8/8/2023 |