Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
01/21/2022
Applicant:
Andrea Flood
Description:
SFR F50A19 T19-M0034

Permit Reviews

Permit Number - T22CM00479
Permit Status: Complete
Permit Description: SFR F50A19 T19-M0034
Start Date Submittal Complete Date Status  
03/02/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/06/2023 APPROVED Review Details

Conditions

Permit Number - T22CM00479
Permit Status: Complete
Permit Description: SFR F50A19 T19-M0034
Date Description Comments
01/21/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
01/21/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 ISACCEPTED AND RELEASED BY PCRWRD

Completed Inspections

Permit Status: Complete
Permit Number: T22CM00479
Permit Description: SFR F50A19 T19-M0034
Total Completed Inspections - 19
Date Description Inspector Results Comments
03/24/2022 COT - RSPL - Sewer Passed {Activity date: 03/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
03/24/2022 COT - RSPL - Rough Soil Passed {Activity date: 03/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
03/31/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 03/31/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
03/31/2022 COT - RSBU - Preslab Passed {Activity date: 03/31/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
03/31/2022 COT - RSEL - Electrical Underground Passed {Activity date: 03/31/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
03/31/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/31/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
05/12/2022 COT - RSBU - Roof Nailing Passed {Activity date: 05/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
05/12/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 05/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
10/07/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
10/07/2022 COT - LCBU - Framing Passed {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
10/07/2022 COT - RSEL - Construction Power Passed {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP
TEP ECO}
10/07/2022 BULD - Electrical Clearance Passed {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - CODE ECO}
01/04/2023 COT - BULD - SWG Clearance Passed SWG clearance required
01/04/2023 COT - RSPL - Plumbing Final Passed
01/13/2023 COT - RSPL - Yard Water Line Passed
01/13/2023 COT - RSME - Mechanical Final Passed
01/13/2023 COT - RSEL - Outdoor Lighting Passed
01/18/2023 COT - RSEL - Electrical Final Passed
01/18/2023 RSBU - Building Final Passed

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW
1_ST SEWER ACCEPTANCE LETTER_V1.PDF DOCUMENTS VIEW