Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM00422
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
8640 E BROADWAY BL
Address NEW:
8640 E BROADWAY BL
Apply Date:
01/19/2022
Applicant:
Kristen Spillman / BRR Architecture
Description:
General Remodel. See Cover Sheet. Planning Permit tied to project is DP21-0317
Architects:
- Andrew Maass
Contractors:
- Kristen Spillman / BRR Architecture
Permit Reviews
Permit Number - T22CM00422
Permit Status: Final
Permit Description: General Remodel. See Cover Sheet.
Planning Permit tied to project is DP21-0317
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/19/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 04/12/2022 | COMPLETED |
| 04/28/2022 | RESUBMITTAL | 05/05/2022 | COMPLETED |
| 08/09/2022 | REVISION - - 1ST | 08/23/2022 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T22CM00422
Permit Description: General Remodel. See Cover Sheet.
Planning Permit tied to project is DP21-0317
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/18/2022 | PLUMBING - PROGRESS | RCHANDLER | Approved | -AP. Bathrooms. |
| 07/18/2022 | ELECTRIC - PROGRESS | RCHANDLER | Approved | -AP. Bathrooms. |
| 10/05/2022 | FIRE - FINAL | jfordney | Approved | |
| 10/05/2022 | FIRE - ALARM FINAL | jfordney | Approved | aproved by cgates |
| 10/05/2022 | FIRE SPKLR - FINAL | jfordney | Approved | approved by cbasaldua |
| 10/10/2022 | BUILDING - FINAL | RCHANDLER | Approved | APPROVED BY INSPECTOR AWAITING CONDITIONS |
| 10/10/2022 | ELECTRIC - FINAL | RCHANDLER | Approved | AP |
| 10/10/2022 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | AP |
| 10/10/2022 | MECHANICAL - FINAL | RCHANDLER | Approved | AP |
| 10/10/2022 | FRAMING | RCHANDLER | Approved | AP |
| 10/10/2022 | BUILDING ABOVE CEILING | RCHANDLER | Approved | AP |
| 10/10/2022 | SHEET ROCK NAILING | RCHANDLER | Approved | AP |
| 10/10/2022 | BUILDING - PROGRESS | RCHANDLER | Approved | AP |
| 10/10/2022 | BUILDING - FINAL | RCHANDLER | Approved | AP |
| 10/10/2022 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | AP |
| 10/10/2022 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | AP |
| 10/10/2022 | PLUMBING - PRE SLAB | RCHANDLER | Approved | 1090.AP |
| 10/10/2022 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | AP |
| 10/10/2022 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | AP |
| 10/10/2022 | PLUMBING - FINAL | RCHANDLER | Approved | AP |
| 10/10/2022 | MECHANICAL - PROGRESS | RCHANDLER | Approved | AP |
| 10/10/2022 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | NA |
| 10/10/2022 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | NA |
| 10/10/2022 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | NA |