Permit: T22CM00309
Permit Details
Apply Date:
01/14/2022
Applicant:
TECHNICIANS FOR SUSTAINABILITY
Description:
roof mount 8.80 kW photovoltaic solar system; 22 modules, 2 branches, PV subpanel, 40A PV breaker on 225A bus with 200A MCB, new load center and meter main
Contractors:
- TECHNICIANS FOR SUSTAINABILITY INC
Permit Reviews
Permit Number - T22CM00309
Permit Status: Final
Permit Description: roof mount 8.80 kW photovoltaic solar system; 22 modules, 2 branches, PV subpanel, 40A PV breaker on 225A bus with 200A MCB, new load center and meter main
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2022 | OTHER | 02/03/2022 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T22CM00309
Permit Description: roof mount 8.80 kW photovoltaic solar system; 22 modules, 2 branches, PV subpanel, 40A PV breaker on 225A bus with 200A MCB, new load center and meter main
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2022 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | AP 2090 |
| 03/09/2022 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE DGC |
| 03/09/2022 | ELECTRIC - FINAL | RCHANDLER | Approved | AP. DGC clearance for TEP. Field 12-2 |
| 03/09/2022 | BUILDING - FINAL | RCHANDLER | Approved | AP |