Permit: T22CM00303
Permit Details
Apply Date:
01/14/2022
Applicant:
RAMON VALDEZ
Description:
NEW SFRS VALD000119 T19-M003 T22-M0013
Contractors:
- VAL VAL CONSTRUCTION LLC
Permit Reviews
Permit Number - T22CM00303
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
T22-M0013
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 02/28/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM00303
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
T22-M0013
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/14/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T22CM00303
Permit Description: NEW SFRS VALD000119 T19-M003
T22-M0013
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2022 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | Approved, okay to backfill |
| 03/02/2022 | PLUMBING - SEWER HCS CONNECT | TGAUSP | Approved | Approved, okay to backfill |
| 03/02/2022 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved |
| 03/04/2022 | ELECTRIC - UFER | TGAUSP | Approved | Approved |
| 03/04/2022 | BUILDING PRE-SLAB | TGAUSP | Approved | Approved |
| 03/04/2022 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved |
| 03/14/2022 | ROOF NAILING | WGALLAGHER | Approved | Approved |
| 03/14/2022 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Approved |
| 03/17/2022 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 03/17/2022 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 03/17/2022 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | Approved |
| 03/17/2022 | FRAMING | DMUNIZ | Approved | Approved |
| 03/25/2022 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE ECO |
| 03/25/2022 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | Approved, please send ECO Clearance to TEP for the construction power |
| 05/02/2022 | BUILDING - FINAL | TGAUSP | Approved | Approved |
| 05/02/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | 1090.Approved |
| 05/02/2022 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
| 05/02/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | 1090.Approved |
| 05/02/2022 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
| 05/02/2022 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |