Permit: T22CM00281
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2815 E 2ND ST
Address NEW:
2815 E 2ND ST
Apply Date:
01/13/2022
Applicant:
Description:
R-Addition Bedrooms and Porch
Permit Reviews
Permit Number - T22CM00281
Permit Status: Complete
Permit Description: R-Addition Bedrooms and Porch
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/13/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 02/17/2022 | COMPLETED |
| 03/24/2022 | RESUBMITTAL | 03/30/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM00281
Permit Status: Complete
Permit Description: R-Addition Bedrooms and Porch
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/30/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00281
Permite Description: R-Addition Bedrooms and Porch
Total Outstanding Inspections - 12
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2022 | COT - LCBU - Framing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - HCBU - Interior Shear Bracing | N/A | Canceled | Inspection Canceled |
| 11/20/2023 | COT - RSPL - Sewer | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSPL - Rough Soil | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSBU - Masonry Pregrout | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSBU - Roof Nailing | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSPL - Yard Water Line | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSBU - Interior Shear Bracing | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
| 11/20/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Canceled | Not ready for inspection. Called in by mistake per Jon Goff. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00281
Permit Description: R-Addition Bedrooms and Porch
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/05/2023 | COT - RSPL - Sewer | Passed | Ok to cover progress areas. | |
| 12/05/2023 | COT - RSPL - Rough Soil | Passed | Ok to cover progress areas. | |
| 12/12/2023 | COT - RSBU - Preslab | Passed | This inspection is to include excavation layout and rebar which was previously closed out on this permit. OK to place concrete in progress areas. | |
| 01/02/2024 | COT - RSBU - Masonry Pregrout | Passed | 1/02/24 last lift ok to grout using #4 rebar | |
| 02/02/2024 | COT - RSBU - Roof Nailing | Passed | 2/2/24: Porch roof is properly nailed off. Okay to proceed with roofing materials. | |
| 02/21/2024 | COT - RSPL - Yard Water Line | Passed | 2/21/24: Water line is connected to City water meter and under pressure. Okay to shade pipe and backfill trench. | |
| 02/29/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 02/29/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 03/06/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 3/6/24: Light fixture and receptacle have been installed at attic access point, DWV is full of water with no leaks, and an exhaust fan has been installed in laundry area. | |
| 06/07/2024 | RSBU - Building Final | Passed | ||
| 06/07/2024 | COT - RSEL - Electrical Final | Passed | ||
| 06/07/2024 | COT - RSME - Mechanical Final | Passed | ||
| 06/07/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 06/07/2024 | RSME - Mechanical Progress | Passed |