Permit: T22CM00246
Permit Details
Apply Date:
01/12/2022
Applicant:
Technicians for Sustainability
Description:
329.42 kW DC PV system on 2 new custom steel canopies in south parking lot - replacing existing parking canopies.. Grid-tied inverters will supply power through existing TEP service.
Contractors:
- Technicians for Sustainability
Permit Reviews
Permit Number - T22CM00246
Permit Status: Final
Permit Description: 329.42 kW DC PV system on 2 new custom steel canopies in south parking lot - replacing existing parking canopies.. Grid-tied inverters will supply power through existing TEP service.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/12/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 02/24/2022 | COMPLETED |
07/28/2022 | 3RD PARTY REVIEW - REVISION/OTHER | 09/16/2022 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T22CM00246
Permit Description: 329.42 kW DC PV system on 2 new custom steel canopies in south parking lot - replacing existing parking canopies.. Grid-tied inverters will supply power through existing TEP service.
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/11/2022 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
05/11/2022 | ELECTRIC - UFER | DQUINN | Approved | Ap Last 8 columns and ufer ok to pour for P-2 array. |
06/14/2022 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ap Remainder of conduit run, from parking lot to building risers, ok Note: 3’ depth not available in this area. It will be covered with painted concrete and caution tape. |
07/21/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
07/21/2022 | ELECTRIC - PROGRESS | DQUINN | Approved | Ap |
07/21/2022 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap |
07/21/2022 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap |
07/21/2022 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
07/21/2022 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
07/21/2022 | FRAMING | DQUINN | Approved | Ap |
07/21/2022 | ROOF NAILING | DQUINN | Approved | Ap |
07/21/2022 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | Ap |
09/27/2022 | BUILDING - FINAL | TGAUSP | Approved |