Permit: T22CM00128
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
5301 S NOGALES HY BLDG 3
Address NEW:
5301 S NOGALES HY BLDG 3
Apply Date:
01/06/2022
Applicant:
Alex Pillion
Description:
New Multi-family Development Building 3
Permit Reviews
Permit Number - T22CM00128
Permit Status: Complete
Permit Description: New Multi-family Development Building 3
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 02/04/2022 | COMPLETED |
| 02/26/2022 | RESUBMITTAL | 03/17/2022 | COMPLETED |
| 04/15/2022 | RESUBMITTAL | 04/26/2022 | COMPLETED |
| 01/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/25/2024 | APPROVED |
| 01/31/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/02/2024 | REQUIRES RESUBMIT |
| 02/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 02/26/2024 | APPROVED |
| 01/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/29/2024 | APPROVED |
Conditions
Permit Number - T22CM00128
Permit Status: Complete
Permit Description: New Multi-family Development Building 3
| Date | Description | Comments |
|---|---|---|
| 01/26/2024 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 04/18/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 04/18/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 04/18/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 04/18/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 04/18/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 04/18/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/26/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
| 04/18/2022 | SHOP DRAWINGS REQUIRED FOR FIRE SPRINKLERS | |
| 04/18/2022 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM | |
| 04/18/2022 | SHOP DRAWINGS REQUIRED FOR WOOD TRUSSES | |
| 02/26/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 02/26/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 04/26/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. | |
| 02/26/2024 | SPECIAL INSPECTION FOR SHOTCRETE IS REQUIRED. | |
| 02/20/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 01/30/2024 | SPECIAL INSPECTION FOR structural steel IS REQUIRED | |
| 02/26/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 01/26/2024 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 02/26/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00128
Permite Description: New Multi-family Development Building 3
Total Outstanding Inspections - 15
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Sewer | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Roof Nailing | N/A | Not Ready | |
| 10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Roof Drains | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 08/31/2023 | COT - LCEL - Electrical Progress | N/A | Partial Pass | Partial, in wall area behind electrical meter panels, ok to insulate and drywall. 8/31/23 |
| 12/17/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
| 12/18/2023 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 01/18/2024 | COT - LCEL - Electrical Final | N/A | Partial Pass | |
| 01/18/2024 | COT - LCBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00128
Permit Description: New Multi-family Development Building 3
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/29/2022 | COT - LCBU - Preslab | Passed | ||
| 12/09/2022 | COT - LCPL - Sewer | Passed | Approved 4” connected to HCS, okay to backfill progress areas | |
| 01/13/2023 | COT - LCPL - Yard Water Line | Passed | ||
| 02/21/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | Building #3. | |
| 02/21/2023 | COT - LCBU - Roof Nailing | Passed | Building #3. | |
| 03/17/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 03/17/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 03/17/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
| 05/25/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 05/25/2023 | COT - LCPL - Plumbing Progress | Passed | ||
| 05/25/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
| 07/11/2023 | COT - FCON - Underground Pressure | Passed | ||
| 09/26/2023 | COT - LCEL - Electrical Progress | Passed | 9/26/23 ok for clearance ECO for building 3 units 3101, 3102, 3103, 3104, 3201, 3202, 3203, 3204, 3301, 3302, 3303, 3304 and HOUSE PANEL | |
| 12/13/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 12/17/2023 | COT - LCBU - Framing | Passed | ||
| 12/17/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 12/17/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 12/17/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 12/17/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 12/18/2023 | COT - FCON - Underground Flush | Passed | ||
| 12/17/2023 | COT - HCPL - Plumbing Progress | Passed | ||
| 12/17/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 12/17/2023 | COT - LCBU - Building Progress | Passed | ||
| 12/17/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 12/17/2023 | COT - LCPL - Backwater Valve | Passed | ||
| 12/17/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
| 12/21/2023 | COT - FCON - Alarm - Final | Passed | ||
| 12/21/2023 | COT - FCON - Sprinkler - Final | Passed | ||
| 12/21/2023 | COT - FCON - Fire - Final | Passed | ||
| 12/21/2023 | FCON – OH Piping & Hydro | Passed | ||
| 01/18/2024 | COT - LCME - Mechanical Final | Passed | ||
| 01/18/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 01/23/2024 | COT - LCEL - Electrical Final | Passed | ||
| 01/31/2024 | COT - LCBU - Building Final | Passed | 12/15/23: UV Coat all vents going trough the roof, properly secure drainage of water heater pan in order to have proper air gap, Appliances need to be installed to ensure proper connections and install. Ok for level 2 TCO 12/29/23: TCofO Level 4 1/31/24: ok for CofO |