Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
01/06/2022
Applicant:
Don Vigil
Description:
New Multi-family Development Building 1

Permit Reviews

Permit Number - T22CM00114
Permit Status: Complete
Permit Description: New Multi-family Development Building 1
Start Date Submittal Complete Date Status  
01/06/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 02/04/2022 COMPLETED Review Details
02/26/2022 RESUBMITTAL 03/17/2022 COMPLETED Review Details
04/15/2022 RESUBMITTAL 04/26/2022 COMPLETED Review Details
01/31/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/02/2024 REQUIRES RESUBMIT Review Details
01/29/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/29/2024 APPROVED Review Details
02/12/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 02/13/2024 APPROVED Review Details
01/25/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/25/2024 APPROVED Review Details

Conditions

Permit Number - T22CM00114
Permit Status: Complete
Permit Description: New Multi-family Development Building 1
Date Description Comments
04/18/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
04/18/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
04/18/2022 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
04/18/2022 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
04/18/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
04/18/2022 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/18/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/18/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
04/26/2022 This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm
04/18/2022 SHOP DRAWINGS REQUIRED FOR FIRE SPRINKLERS
04/18/2022 SHOP DRAWINGS REQUIRED FOR FIRE ALARMS
04/18/2022 SHOP DRAWINGS REQUIRED FOR WOOD TRUSSES
02/13/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/26/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS.
01/30/2024 SPECIAL INSPECTION FOR structural steel IS REQUIRED

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM00114
Permite Description: New Multi-family Development Building 1
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCPL - Rough Soil N/A Not Ready
10/26/2022 COT - LCPL - Sewer N/A Not Ready
10/26/2022 COT - LCBU - Preslab N/A Not Ready
10/26/2022 COT - LCBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Roof Drains N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Above Ceiling N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Progress N/A Not Ready
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning N/A Not Ready
10/25/2023 BULD - Electrical Clearance N/A Not Ready
12/07/2023 COT - LCME - Mechanical Final N/A Not Ready 12/7/23: not ready
12/07/2023 COT - LCPL - Plumbing Final N/A Not Ready
12/07/2023 COT - LCEL - Electrical Final N/A Not Ready 12/7/23: not ready
01/25/2024 COT - LCBU - Building Final N/A Partial Pass 1/23/24: weather strips at door missing on all units, no access to roof.
1/25/24: Level 4 TCO. Pending water sterilization report and air balance report for building final.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM00114
Permit Description: New Multi-family Development Building 1
Total Completed Inspections - 37
Date Description Inspector Results Comments
11/10/2022 COT - LCPL - Rough Soil Passed approved. okay to backfill. shading required.
12/01/2022 COT - LCEL - Grounding/Bonding Passed Ufer ground
12/09/2022 COT - LCPL - Sewer Passed Approved 4” connected to HCS, okay to backfill progress areas
12/19/2022 COT - LCBU - Stem Wall/Retaining Wall Passed
01/13/2023 COT - LCPL - Yard Water Line Passed
02/08/2023 COT - LCBU - Preslab Passed
03/28/2023 COT - LCBU - Exterior Clips/Sheathing Passed Corrections were made. 3/28/2023
05/03/2023 COT - LCPL - Plumbing Intermediate Passed Plumbing WDV are under water test and it is holding. All penetration through top plates are fire caulked. Water supply lines are under 120+ psi of compressed air. Okay to insulate and sheet rock walls.
05/03/2023 COT - LCPL - Plumbing Roof Drains Passed Roof drains are under water test and holding.
06/26/2023 COT - LCME - Mechanical Progress Passed
06/26/2023 COT - LCEL - Electrical Progress Passed
06/26/2023 COT - LCME - Mechanical Intermediate Passed
06/26/2023 COT - LCPL - Plumbing Above Ceiling Passed
06/26/2023 COT - LCPL - Plumbing Progress Passed
07/11/2023 COT - FCON - Underground Pressure Passed
08/17/2023 COT - LCBU - Excavation/Rebar/Zoning Passed 8/17/23 partial approval for 10 light pole bases OK to place concrete
12/07/2023 COT - LCBU - Building Above Ceiling Passed
12/07/2023 COT - LCBU - Framing Passed
12/07/2023 COT - LCME - Mechanical Above Ceiling Passed
12/07/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
12/07/2023 COT - LCBU - Sustainability Passed
12/07/2023 COT - LCEL - Electrical Above Ceiling Passed
12/07/2023 BULD - Electrical Clearance Passed
12/07/2023 COT - LCBU - Building Progress Passed
12/07/2023 COT - HCBU - Interior Shear Bracing Passed
12/07/2023 COT - LCPL - Backwater Valve Passed
12/13/2023 COT - LCEL - Outdoor Lighting Passed
12/14/2023 COT - LCEL - Electrical Intermediate Passed
12/21/2023 COT - FCON - Underground Flush Passed
12/21/2023 COT - FCON - Alarm - Final Passed
12/21/2023 COT - FCON - Sprinkler - Final Passed
12/21/2023 COT - FCON - Fire - Final Passed
12/21/2023 FCON – OH Piping & Hydro Passed
01/25/2024 COT - LCME - Mechanical Final Passed
01/25/2024 COT - LCPL - Plumbing Final Passed
01/25/2024 COT - LCEL - Electrical Final Passed
01/31/2024 COT - LCBU - Building Final Passed 1/23/24: weather strips at door missing on all units, no access to roof.
1/25/24: Level 4 TCO. Pending water sterilization report and air balance report for building final.
1/31/24: Ok for CofO

Documents

File Name Document Type  
GCL 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
NEWPORT BUILDING 1 - UPDATED-2024-02-12_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
10351 NEWPORT AT THE RODEO SPECIAL INSPECTION FINAL PACKET-2024-01-28_V1.PDF DOCUMENTS VIEW
10351 NAR WATER TESTING REPORT FOR BLDGS 1,2,3,4 (1)-2024-01-25_V1.PDF DOCUMENTS VIEW
NEWPORT AT THE RODEO - BUILDING 1 REPORT (1)_V1.PDF DOCUMENTS VIEW
GCL.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
SOILS REPORT.PDF DOCUMENTS VIEW
SPECS.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
ZONING DECISION LETTER.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW