Permit: T21CM09963
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
2017 N TUCSON BL
Address NEW:
2017 N TUCSON BL
Apply Date:
12/30/2021
Applicant:
Description:
R-Enclose Carport and Bedroom Suite Addition
Outstanding Activity Conditions
Permit Number - T21CM09963
Permit Status: Issued
Permit Description: R-Enclose Carport and Bedroom Suite Addition
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 03/16/2022 | FUP T22OT00016 MUST BE PAID BEFORE FINAL INSPECTIONS. |
| 04/04/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM09963
Permite Description: R-Enclose Carport and Bedroom Suite Addition
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
| 01/05/2023 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 01/05/2023 | COT - RSME - Mechanical Final | N/A | Not Ready | |
| 01/05/2023 | COT - RSEL - Electrical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09963
Permit Description: R-Enclose Carport and Bedroom Suite Addition
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2022 | COT - RSPL - Sewer | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 08/03/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 08/15/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/15/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 08/15/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/15/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 01/05/2023 | COT - LCBU - Framing | Passed | ||
| 01/05/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 01/05/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 01/05/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
| 02/09/2023 | COT - HCBU - Interior Shear Bracing | Passed | ok to mud and tape kitchen and front area of house |