Permit: T21CM09904
Permit Details
Apply Date:
12/27/2021
Applicant:
Description:
SFR LENNVC352 T20-M0029
Outstanding Activity Conditions
Permit Number - T21CM09904
Permit Status: Issued
Permit Description: SFR LENNVC352 T20-M0029
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/27/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09904
Permit Description: SFR LENNVC352 T20-M0029
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/11/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 02/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
02/11/2022 | COT - RSPL - Sewer | Passed | {Activity date: 02/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
02/11/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 02/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/09/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/09/2022 | COT - RSBU - Preslab | Passed | {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/09/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/09/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/29/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 03/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
03/29/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 03/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
06/03/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 06/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO} | |
06/03/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 06/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP TEP ECO} |
|
06/10/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/09/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - corrections required, re locate plumbing vent to provide 10’ clearance from fresh air intake. Install nail plate for water lines where required.} | |
06/10/2022 | RSME - Mechanical Progress | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/09/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
06/10/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/09/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Corrections required, gas pressure test failed.} | |
06/13/2022 | COT - LCBU - Framing | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: TLUNBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/10/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - corrections required, install nail pate @rear hose bib line at top plate, nail interior bearing clips roof is loaded.} ; {Activity date: 06/09/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - corrections required, nail clips @ interior bearing points. Roof is loaded.} | |
06/21/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 06/21/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
08/22/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - CODE} | |
08/29/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/10/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Corrections required. } ; {Activity date: 06/09/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} |
|
08/29/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Provide proper spacing for condenser. Per cut sheet } |
|
08/29/2022 | RSBU - Building Final | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready.} | |
08/29/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/29/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Cut out door plumbing to grade level also fix one that was broken} ; {Activity date: 08/22/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Clearance for southwest gas. } |
|
08/29/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Electrical outlets are not wired properly. } |