Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
12/27/2021
Applicant:
Description:
SFR LENNVC352 T20-M0029

Outstanding Activity Conditions

Permit Number - T21CM09904
Permit Status: Issued
Permit Description: SFR LENNVC352 T20-M0029
Total Outstanding Activity Conditions - 1
Date Name
12/27/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Issued
Permit Number: T21CM09904
Permit Description: SFR LENNVC352 T20-M0029
Total Completed Inspections - 23
Date Description Inspector Results Comments
02/11/2022 COT - RSPL - Yard Water Line Passed {Activity date: 02/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/11/2022 COT - RSPL - Sewer Passed {Activity date: 02/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/11/2022 COT - RSPL - Rough Soil Passed {Activity date: 02/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/09/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/09/2022 COT - RSBU - Preslab Passed {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/09/2022 COT - RSEL - Electrical Underground Passed {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/09/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/29/2022 COT - RSBU - Roof Nailing Passed {Activity date: 03/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
03/29/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 03/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
06/03/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 06/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO}
06/03/2022 COT - RSEL - Construction Power Passed {Activity date: 06/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP
TEP ECO}
06/10/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 06/10/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/09/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - corrections required, re locate plumbing vent to provide 10’ clearance from fresh air intake. Install nail plate for water lines where required.}
06/10/2022 RSME - Mechanical Progress Passed {Activity date: 06/10/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/09/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready}
06/10/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 06/10/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/09/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Corrections required, gas pressure test failed.}
06/13/2022 COT - LCBU - Framing Passed {Activity date: 06/13/2022; Status: Approved; Inspector: TLUNBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/10/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - corrections required, install nail pate @rear hose bib line at top plate, nail interior bearing clips roof is loaded.} ; {Activity date: 06/09/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - corrections required, nail clips @ interior bearing points. Roof is loaded.}
06/21/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 06/21/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
08/22/2022 COT - BULD - SWG Clearance Passed {Activity date: 08/22/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - CODE}
08/29/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/10/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Corrections required.
} ; {Activity date: 06/09/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready}
08/29/2022 COT - RSME - Mechanical Final Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Provide proper spacing for condenser. Per cut sheet

}
08/29/2022 RSBU - Building Final Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready.}
08/29/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
08/29/2022 COT - RSPL - Plumbing Final Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Cut out door plumbing to grade level also fix one that was broken} ; {Activity date: 08/22/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Clearance for southwest gas.

}
08/29/2022 COT - RSEL - Electrical Final Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/25/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Electrical outlets are not wired properly.
}

Documents

File Name Document Type  
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
VC 101 352 AR9 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
VC 101 352 PERMIT APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
VC 101 SPECIAL INSPECTION CERT 2-18-2020 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
VC 101 352 AR9.PDF DOCUMENTS VIEW
VC 101 352 PERMIT APPLICATION.PDF DOCUMENTS VIEW
VC 101 SPECIAL INSPECTION CERT 2-18-2020.PDF DOCUMENTS VIEW