Permit: T21CM09889
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
2435 N SANTA RITA AV
Address NEW:
2435 N SANTA RITA AV
Apply Date:
12/27/2021
Applicant:
Cyrus Moore
Description:
SFR 1 of 2 - RESIDENCE 1 = 1493 SF
Permit Reviews
Permit Number - T21CM09889
Permit Status: Issued
Permit Description: SFR 1 of 2 - RESIDENCE 1 = 1493 SF
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2022 | RESUBMITTAL | 03/21/2022 | COMPLETED |
| 05/10/2022 | REVISION - - 1ST | 05/17/2022 | COMPLETED |
| 12/27/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 01/28/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM09889
Permit Status: Issued
Permit Description: SFR 1 of 2 - RESIDENCE 1 = 1493 SF
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 02/02/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 02/02/2022 | SPECIAL INSPECTION IS REQUIRED FOR POST INSTALLED ANCHORS |
Conditions
Permit Number - T21CM09889
Permit Status: Issued
Permit Description: SFR 1 of 2 - RESIDENCE 1 = 1493 SF
| Date | Description | Comments |
|---|---|---|
| 03/21/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
| 03/21/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09889
Permit Description: SFR 1 of 2 - RESIDENCE 1 = 1493 SF
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/25/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 05/06/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/06/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Ok to backfill to meter.} |
|
| 05/20/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/03/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
| 05/31/2022 | COT - LCBU - Framing | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/20/2022; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - not ready} ; {Activity date: 05/03/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
| 05/31/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 05/31/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/24/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. Missing anchor bolts. } ; {Activity date: 05/20/2022; Status: Denied; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Denied. Missing interior sheer wall panels, missing rafter bracing. STOPPED INSPECTION.} ; {Activity date: 05/03/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready Note: Set back requirements not per plan, stopped inspection. Submit revision and provide approved plan set on site reflecting as built and fire assembly detail. } |
|
| 05/31/2022 | RSEL - Electrical Progress | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 05/31/2022 | RSME - Mechanical Progress | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 06/09/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - CODE ECO FOR UNITS #1 & #2} | |
| 06/09/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. For units #1 & #2. The TEP clearance code is ECO.} | |
| 06/24/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 06/24/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap Fire, shear, and regular} |
|
| 07/15/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 07/15/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 07/15/2022 | COT - RSBU - Preslab | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 07/15/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 07/15/2022 | COT - RSPL - Sewer | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/01/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa 3” abs running from back to fence corner at front, ok to backfill.} |
|
| 07/15/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 09/07/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved Please close out this permit.} |
|
| 09/07/2022 | RSBU - Building Final | Passed | {Activity date: 09/07/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS } ; {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved Please close out this permit.} |
|
| 09/07/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved Please close out this permit.} |
|
| 09/07/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved Please close out this permit.} |
|
| 09/07/2022 | COT - RSBU - Sustainability | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved Please close out this permit.} |
|
| 09/07/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved Please close out this permit.} |