Permit: T21CM09875
Permit Details
Apply Date:
12/27/2021
Applicant:
Papo Construction/ Brandon Filipp Project Manager
Description:
Gas line inspection/ pressure test
Contractors:
- Papo Construction
Completed Inspections
Permit Status: Final
Permit Number: T21CM09875
Permit Description: Gas line inspection/ pressure test
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/03/2022 | PLUMBING - FINAL | JBURGE | Approved | Approved Called in to SW Gas at 1000 hours. Please close out this permit. **FEE BALANCE REQUIRES TO BE ZERO.** |
| 01/03/2022 | GAS CLEARANCE | JBURGE | Approved | CODE |
| 01/03/2022 | PLUMBING - GAS RECONNECT | JBURGE | Approved | Approved |
| 01/03/2022 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | Approved |