Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Address NEW:
1341 N FALCON RIDGE DR
Apply Date:
12/23/2021
Applicant:
Description:
REPAIR FIRE DAMAGES TO RESIDENCE, REPLACE PORCH, RECONNECT GAS AND ELECTRIC SERVICES

Permit Reviews

Permit Number - T21CM09849
Permit Status: Issued
Permit Description: REPAIR FIRE DAMAGES TO RESIDENCE, REPLACE PORCH, RECONNECT GAS AND ELECTRIC SERVICES
Start Date Submittal Complete Date Status  
01/20/2022 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 02/10/2022 COMPLETED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM09849
Permite Description: REPAIR FIRE DAMAGES TO RESIDENCE, REPLACE PORCH, RECONNECT GAS AND ELECTRIC SERVICES
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
01/10/2023 COT - RSEL - Electrical Final N/A Not Ready
01/10/2023 RSBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T21CM09849
Permit Description: REPAIR FIRE DAMAGES TO RESIDENCE, REPLACE PORCH, RECONNECT GAS AND ELECTRIC SERVICES
Total Completed Inspections - 14
Date Description Inspector Results Comments
04/20/2022 COT - RSBU - Roof Nailing Passed {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/20/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/20/2022 COT - LCBU - Framing Passed {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/20/2022 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/20/2022 RSME - Mechanical Progress Passed {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved

CLEARANCE ; Code: RECN}
07/06/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE RECN} ; {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE RECN}
07/06/2022 COT - RSPL - Plumbing Final Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR}
07/06/2022 COT - BULD - SWG Clearance Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE}
07/06/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/20/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by VVERA1 - Not ready. Gas line not under test pressure.}
07/06/2022 COT - RSPL - Gas Reconnect Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, please send Clearance to SWG for the meter reconnection} ; {Activity date: 04/20/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by VVERA1 - Not ready. Gas line not under test pressure.}
07/06/2022 COT - RSEL - Electrical Reconnect Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, please send RECN Clearance to TEP for the service reconnection} ; {Activity date: 04/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to energize service
}
08/09/2022 COT - RSME - Mechanical Final Passed {Activity date: 08/09/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 07/06/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR}
02/03/2023 COT - RSEL - Electrical Final Passed
02/03/2023 RSBU - Building Final Passed