Permit Reviews
Permit Number - T21CM09666
Permit Status: Complete
Permit Description: Tenant Build-Out
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/14/2022 | RESUBMITTAL | 03/17/2022 | COMPLETED |
04/01/2022 | RESUBMITTAL | 04/07/2022 | COMPLETED |
05/23/2022 | REVISION - - 1ST | 06/03/2022 | COMPLETED |
12/17/2021 | COMMERCIAL - TI | 02/10/2022 | COMPLETED |
12/07/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/07/2022 | APPROVED |
Conditions
Permit Number - T21CM09666
Permit Status: Complete
Permit Description: Tenant Build-Out
Date | Description | Comments |
---|---|---|
04/07/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM09666
Permite Description: Tenant Build-Out
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Service Upgrade | N/A | Not Ready | |
11/07/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
11/18/2022 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | Builder wants to get TCO, and will fabricate new ladders and nstall after occupancy. |
10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
11/17/2022 | COT - LCME - Mechanical Final | N/A | Re-inspection required | secure roof access ladders near the top to prevent wobbling. |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | Need knox box near the front entrance. Need fire riser sign on metal door leading to back patio area were the riser is located along with riser sign on the door leading to the riser inside. Need knox sprinkler connection caps on the fdc, and the fire alarm monitoring needs to be tested. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09666
Permit Description: Tenant Build-Out
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/21/2022 | COT - LCBU - Preslab | Passed | {Activity date: 04/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
08/02/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved. Domestic water. } |
|
08/11/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
08/29/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/09/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Partial Approval-Walls and hard lids.} ; {Activity date: 08/02/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Denied. Provide 18” minimum on pull side of doors.} | |
08/29/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/19/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval NORTH OF grid line D OK TO 2 SIDE HARD LIDS AND SOFFITS Including reception area} ; {Activity date: 08/16/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval from grid line C south to 3 east} ; {Activity date: 08/11/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Partial Approval: Corridors.} |
|
09/28/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 09/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - AP. Consultation.} ; {Activity date: 08/19/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - NOT READY } ; {Activity date: 08/02/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Not Ready.} |
|
10/07/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - -AP} | |
10/07/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - -AP} ; {Activity date: 08/24/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Partial Approval: Hard lids.} ; {Activity date: 04/19/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Duct sealing. } |
|
10/07/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - -AP} ; {Activity date: 08/24/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Partial Approval: Hard lids.} | |
10/07/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - -AP} | |
10/26/2022 | COT - FCON - Alarm - Final | Passed | passed by Will Motto on 2/22/2022 | |
11/21/2022 | COT - LCEL - Outdoor Lighting | Passed | ||
11/23/2022 | COT - FCON - Sprinkler - Final | Passed | passed by Will Motto on 2/22/2022 | |
11/21/2022 | COT - LCEL - Electrical Final | Passed | ||
11/22/2022 | COT - LCBU - Building Final | Passed | ||
12/01/2022 | COT - FCON - Fire - Final | Passed |