Permit Details

Status:
Issued
Type:
Commercial Building
Address:
6960 E 22ND ST
Apply Date:
12/13/2021
Applicant:
Lisa Bowers
Description:
Shell remodel for future Starbucks

Permit Reviews

Permit Number - T21CM09487
Permit Status: Issued
Permit Description: Shell remodel for future Starbucks
Start Date Submittal Complete Date Status  
02/22/2022 RESUBMITTAL 03/03/2022 COMPLETED Review Details
03/04/2022 RESUBMITTAL 03/04/2022 COMPLETED Review Details
12/13/2021 3RD PARTY REVIEW - COMMERCIAL TI 02/22/2022 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T21CM09487
Permit Status: Issued
Permit Description: Shell remodel for future Starbucks
Total Outstanding Activity Conditions - 4
Date Name
02/22/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
02/22/2022 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
02/22/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/22/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.

Completed Inspections

Permit Status: Issued
Permit Number: T21CM09487
Permit Description: Shell remodel for future Starbucks
Total Completed Inspections - 13
Date Description Inspector Results Comments
05/09/2022 COT - LCPL - Sewer Passed {Activity date: 05/09/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP}
08/03/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Approved; balance of Plumbing will be done with TI.} ; {Activity date: 07/20/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Builder scheduled to have framing looked at; OK to dry in.} ; {Activity date: 07/19/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled}
08/24/2022 COT - LCBU - Preslab Passed {Activity date: 08/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved. Contractor wanted footings for dumpster, referred to Dave for Engineering inspection.} ; {Activity date: 08/12/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - PA
Ok to pour main floor} ; {Activity date: 06/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Pad footings.}
09/01/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved

CLEARANCE: Code: ECO. Ok to energize electrical system.
} ; {Activity date: 08/03/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Partial Approval; all work complete for shell. Left open as no service clearance inspection is on permit.} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Outside.} ; {Activity date: 05/17/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. UG in building footprint.}
09/02/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 09/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - CODE ECO}
10/10/2022 COT - LCBU - Building Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/30/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Remainder of finals to be completed on TI.}
10/10/2022 COT - LCME - Mechanical Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/30/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Remainder of mechanical intermediate to be completed on TI.

}
10/10/2022 COT - LCEL - Outdoor Lighting Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/12/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Partial Approval. Structural for signs and menu board; location by development plan.} ; {Activity date: 09/08/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} ; {Activity date: 08/30/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Menu board needs to be completed.}
10/10/2022 COT - LCEL - Electrical Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/30/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Exterior 200 amp disconnects (3) and meter box.
Intermediate to be completed on TI.}
10/10/2022 COT - LCPL - Rough Soil Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Water line to landscape.

} ; {Activity date: 05/09/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Outside including grease trap.}
10/10/2022 COT - FCON - Fire - Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } ; {Activity date: 08/30/2022; Status: Cancelled; Inspector: jfordney; Comment: Entered by JFORDNE1 - not ready}
10/10/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP}
10/10/2022 COT - LCPL - Plumbing Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP} ; {Activity date: 08/30/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Remainder of plumbing intermediate to be completed on TI.}

Documents

File Name Document Type  
PLAN SET.PDF CONSTRPLANS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PSA.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW