SFR RICHT920 T19-M0085
Outstanding Activity Conditions
Permit Number - T21CM09470
Permit Status: Issued
Permit Description: SFR RICHT920 T19-M0085
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/13/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09470
Permit Description: SFR RICHT920 T19-M0085
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/04/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
01/04/2022 | COT - RSPL - Sewer | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
01/04/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
01/18/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 01/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/18/2022 | COT - RSBU - Preslab | Passed | {Activity date: 01/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/18/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 01/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/18/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 01/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/26/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/26/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/23/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO} | |
03/23/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP TEP ECO} ; {Activity date: 03/14/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CO 1. Install a GFCI breaker 2. Install a in-use cover over receptacle} |
|
04/12/2022 | COT - LCBU - Framing | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/12/2022 | RSME - Mechanical Progress | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/12/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/14/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/13/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready see previous results 4/12 } ; {Activity date: 04/12/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, see plumbing notes.} |
|
04/14/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/13/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready see previous results 4/12 } ; {Activity date: 04/12/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready, provide DWV test} |
|
04/22/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 04/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
06/14/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 06/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
06/21/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 06/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/17/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} | |
06/21/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 06/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
06/21/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 06/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/17/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} ; {Activity date: 06/14/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA SWG clearance required} |
|
06/21/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 06/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/17/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} | |
06/29/2022 | RSBU - Building Final | Passed | {Activity date: 06/29/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS } ; {Activity date: 06/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/24/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS } ; {Activity date: 06/21/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR 1.replace missing sidewalk in front of driveway 2. Remove dumpster and extra fence block in front yard} ; {Activity date: 06/17/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR 1. Water heater B-vent incomplete 2. Install side gate 3. Secure NMC at AC to the house. 4. Remove all unused tile from the roof.} |