Permit: T21CM09431
Permit Details
Apply Date:
12/10/2021
Applicant:
Andrea Flood
Description:
SFR F50C19 T19-M0032
Outstanding Activity Conditions
Permit Number - T21CM09431
Permit Status: Issued
Permit Description: SFR F50C19 T19-M0032
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/10/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09431
Permit Description: SFR F50C19 T19-M0032
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/09/2022 | COT - RSPL - Sewer | Passed | {Activity date: 02/09/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
02/17/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
02/17/2022 | COT - RSBU - Preslab | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
02/17/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
02/17/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
04/14/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/12/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
04/14/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/12/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval missing H2.5 on posts and nail strips on glue lamb rear patio} | |
06/15/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 06/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO} | |
06/15/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 06/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP TEP ECO} |
|
08/31/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/31/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval ok to cover no pressure on line } |
|
08/31/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/31/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
09/19/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
11/16/2022 | COT - LCBU - Framing | Passed | ||
11/16/2022 | COT - RSPL - Plumbing Final | Passed | SWG clearance required | |
11/28/2022 | COT - RSPL - Rough Soil | Passed | ||
11/28/2022 | COT - RSME - Mechanical Final | Passed | ||
11/30/2022 | COT - RSEL - Outdoor Lighting | Passed | ||
11/30/2022 | COT - RSEL - Electrical Final | Passed | ||
12/01/2022 | RSBU - Building Final | Passed |