Permit: T21CM09369
Permit Details
Apply Date:
12/06/2021
Applicant:
Alexander Anderson
Description:
SFR MPLAN1510 T20-M0040
Permit Reviews
Permit Number - T21CM09369
Permit Status: Complete
Permit Description: SFR MPLAN1510 T20-M0040
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/06/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 01/05/2022 | COMPLETED |
01/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/11/2024 | APPROVED |
Conditions
Permit Number - T21CM09369
Permit Status: Complete
Permit Description: SFR MPLAN1510 T20-M0040
Date | Description | Comments |
---|---|---|
12/06/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
12/06/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
12/06/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
12/06/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
12/06/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
01/11/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
01/25/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09369
Permit Description: SFR MPLAN1510 T20-M0040
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/14/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to backfill} | |
04/14/2022 | COT - RSPL - Sewer | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to backfill} | |
04/14/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
05/10/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
05/16/2022 | COT - RSBU - Preslab | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} ; {Activity date: 05/16/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for garage, okay for concrete placement} | |
05/16/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap Note: 2010 is for island. Ufer was approved in garage footings. } |
|
06/20/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to dry in roof system.} | |
06/20/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover exterior walls.} | |
08/23/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
08/23/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
08/23/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved OK for temp construction power.} | |
08/23/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved CLEARANCE; Code; TMPP} |
|
08/23/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
08/23/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for garage, okay for concrete placement} | |
09/08/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/08/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to insulate and cover walls. } |
|
09/19/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Approved} | |
03/20/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
03/20/2023 | COT - RSEL - Electrical Final | Passed | ||
03/20/2023 | COT - RSME - Mechanical Final | Passed | ||
06/20/2023 | RSBU - Building Final | Passed | ||
06/20/2023 | COT - RSPL - Plumbing Final | Passed |