Permit: T21CM09327
Permit Details
Apply Date:
12/03/2021
Applicant:
Description:
SFR F50B19 T19-M0033
Outstanding Activity Conditions
Permit Number - T21CM09327
Permit Status: Issued
Permit Description: SFR F50B19 T19-M0033
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/03/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM09327
Permite Description: SFR F50B19 T19-M0033
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/06/2022 | COT - RSBU - Exterior Clips/Sheathing | N/A | Canceled | {Activity date: 09/06/2022; Status: Not Applicable; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NA} |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09327
Permit Description: SFR F50B19 T19-M0033
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/28/2022 | COT - RSPL - Sewer | Passed | {Activity date: 02/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/02/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/02/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/28/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO line dry} | |
03/02/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/02/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/28/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO stack dry} | |
03/08/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
03/08/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
03/10/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/10/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/08/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready rebar in contact with soil } |
|
03/10/2022 | COT - RSBU - Preslab | Passed | {Activity date: 03/10/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/08/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval see 2005 } ; {Activity date: 03/07/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR. Missing box & wrap. Cancel all other inspections.} |
|
05/05/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
08/19/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/19/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/19/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/19/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
09/21/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO} | |
09/21/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP. TEP ECO} ; {Activity date: 09/06/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE Install a GFCI outlet at the panel and connect to a 20A breaker } |
|
11/07/2022 | COT - RSPL - Plumbing Final | Passed | SWG clearance required. | |
11/16/2022 | COT - RSEL - Outdoor Lighting | Passed | ||
11/16/2022 | RSBU - Building Final | Passed | ||
11/16/2022 | COT - RSEL - Electrical Final | Passed | ||
11/16/2022 | COT - RSME - Mechanical Final | Passed |