Permit: T21CM09245
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2375 W CALLE RETANA
Address NEW:
2375 W CALLE RETANA
Apply Date:
11/30/2021
Applicant:
Martin Mendoza
Description:
BEDROOM ADDITION
Permit Reviews
Permit Number - T21CM09245
Permit Status: Complete
Permit Description: BEDROOM ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/30/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 01/03/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM09245
Permite Description: BEDROOM ADDITION
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09245
Permit Description: BEDROOM ADDITION
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/07/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved connected to existing sewer, okay to backfill progress areas} | |
| 05/04/2022 | COT - RSBU - Preslab | Passed | {Activity date: 05/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 05/04/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 08/08/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 08/08/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 08/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 09/07/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to insulate and cover walls} | |
| 09/07/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/08/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval call with intermediate inspections } |
|
| 09/07/2022 | RSME - Mechanical Progress | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 01/18/2023 | COT - RSEL - Electrical Final | Passed | ||
| 01/18/2023 | COT - RSME - Mechanical Final | Passed | ||
| 01/18/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 01/18/2023 | RSBU - Building Final | Passed |