Permit Reviews
Permit Number - T21CM09203
Permit Status: Complete
Permit Description: RENOVATION OF EXISTING STRUCTURE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/14/2022 | RESUBMITTAL | 03/02/2022 | COMPLETED |
03/22/2022 | REVISION - - 1ST | 03/22/2022 | COMPLETED |
11/26/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 01/11/2022 | COMPLETED |
04/20/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/25/2023 | APPROVED |
04/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/13/2023 | APPROVED |
Conditions
Permit Number - T21CM09203
Permit Status: Complete
Permit Description: RENOVATION OF EXISTING STRUCTURE
Date | Description | Comments |
---|---|---|
01/11/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
01/11/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
01/11/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
01/11/2022 | SHOP DRAWINGS REQUIRED FOR FIRE SUPRESSION SYSTEM |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM09203
Permite Description: RENOVATION OF EXISTING STRUCTURE
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
02/14/2023 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Not Applicable | |
02/27/2023 | COT - LCPL - Plumbing Roof Drains | N/A | Not Applicable | |
02/27/2023 | COT - LCEL - Temporary Service | N/A | Not Applicable | |
FCON – OH Piping & Hydro | N/A | Not Ready | Per contractor called in wrong inspection. Needs gas meter inspected. | |
02/27/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
02/27/2023 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
02/27/2023 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
COT - FCON - Alarm - Final | N/A | Not Ready | everything was tested and passed. However there needs to be a smoke and a pull station at the panel. | |
COT - FCON - Fire - Final | N/A | Not Ready | Need to see door locks on classroom doors. They may not be keyed from the inside. Need the fire alarm to pass inspection. Need em lights in main room to work. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09203
Permit Description: RENOVATION OF EXISTING STRUCTURE
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/02/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 05/02/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
05/17/2022 | COT - LCBU - Preslab | Passed | {Activity date: 05/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved ok for concrete placement} ; {Activity date: 05/16/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -PA. All except ramp. } ; {Activity date: 05/06/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -CA per text from contractor v} ; {Activity date: 03/25/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CA per phon call from contractor.} |
|
06/24/2022 | COT - LCPL - Backwater Valve | Passed | {Activity date: 06/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
09/29/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 09/29/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP. INCR clearance code for TEP.} ; {Activity date: 09/15/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Partial Approval: Level One walls.} | |
09/29/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/29/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE INCR} | |
10/11/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
11/08/2022 | COT - LCBU - Framing | Passed | ||
12/08/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
12/08/2022 | COT - LCPL - Plumbing Progress | Passed | walls level two. | |
02/27/2023 | COT - BULD - SWG Clearance | Passed | SWG clearance required | |
02/27/2023 | COT - LCPL - Rough Soil | Passed | ||
02/27/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
02/27/2023 | COT - LCME - Mechanical Progress | Passed | ||
02/27/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
02/27/2023 | COT - LCPL - Sewer | Passed | ||
04/12/2023 | FCON – OH Piping & Hydro | Passed | by william motto | |
02/27/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
03/02/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
03/02/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
03/02/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
04/05/2023 | COT - FCON - Sprinkler - Final | Passed | ||
04/05/2023 | COT - FCON - Underground Flush | Passed | There was no underground for this project | |
04/05/2023 | COT - FCON - Underground Pressure | Passed | There was no underground for this project. | |
04/11/2023 | COT - FCON - Alarm - Final | Passed | ||
04/11/2023 | COT - FCON - Fire - Final | Passed | ||
04/11/2023 | COT - LCPL - Plumbing Final | Passed | ||
04/11/2023 | COT - LCME - Mechanical Final | Passed | ||
04/11/2023 | COT - LCEL - Electrical Final | Passed | ||
04/11/2023 | COT - LCBU - Building Final | Passed | ||
04/11/2023 | COT - LCEL - Outdoor Lighting | Passed |