Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
11/26/2021
Applicant:
Description:
Tenant Improvement

Permit Reviews

Permit Number - T21CM09180
Permit Status: Complete
Permit Description: Tenant Improvement
Start Date Submittal Complete Date Status  
06/29/2022 REVISION - - 1ST 07/07/2022 COMPLETED Review Details
08/26/2022 REVISION - - 2ND 08/26/2022 COMPLETED Review Details
11/26/2021 3RD PARTY REVIEW - COMMERCIAL TI 01/11/2022 COMPLETED Review Details
12/29/2022 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/04/2023 APPROVED Review Details

Conditions

Permit Number - T21CM09180
Permit Status: Complete
Permit Description: Tenant Improvement
Date Description Comments
12/27/2021 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
12/27/2021 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.

Completed Inspections

Permit Status: Complete
Permit Number: T21CM09180
Permit Description: Tenant Improvement
Total Completed Inspections - 17
Date Description Inspector Results Comments
04/28/2022 COT - LCBU - Preslab Passed {Activity date: 04/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/13/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 09/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 09/12/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA}
09/23/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 09/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/12/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA northwest corner of MRI room} ; {Activity date: 09/06/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - PA
3/4” plywood on ceiling and walls in MRI room approved per plan, fasteners and schedule per plan} ; {Activity date: 08/18/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
Approved plans do not show details for MRI room materials and how to attach. Resubmit new plans for review and field inspection} ; {Activity date: 08/08/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - PA
1st layer of sheetrock on ceiling of MRI room. Next layer will be plywood.} ; {Activity date: 06/22/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - PA
All Sheetrock except interior of MRI room approved to tape} ; {Activity date: 06/02/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - partial approval for all areas excluding MRI room ok to tape}
10/03/2022 COT - LCBU - Framing Passed {Activity date: 10/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP
Exterior west wall, framing for the window reset.} ; {Activity date: 09/30/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - PA
Infill of west MRI room} ; {Activity date: 09/22/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA. Vertical metal studs in MRI room} ; {Activity date: 09/09/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA. Framing over sheet metal in shielded area at northwest corner of MRI room.} ; {Activity date: 08/04/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA. Hard lid channels in MRI room approved} ; {Activity date: 08/02/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
Ceiling framing in MRI room not per plan} ; {Activity date: 06/21/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
The new structural framing details for the MRI ceiling have not been reviewed & approved by Tucson} ; {Activity date: 06/13/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready lack of drawing detail on wall and ceiling buildout on MRI room

} ; {Activity date: 06/10/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Approved plans not on site for ceiling framing in MRI room

} ; {Activity date: 06/02/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
All rooms except MRI & Control rooms} ; {Activity date: 04/28/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - INSPECTOR TL CHANGED HIS AP FROM 04/28/22 TO PA DUE TO ISSUES FOUND.}
10/06/2022 COT - LCPL - Gas Pressure Test Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP
SWG clearance required} ; {Activity date: 10/05/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE
Install a 15 lb gauge with 1/10th increments}
10/06/2022 COT - BULD - SWG Clearance Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS}
10/10/2022 COT - FCON - Alarm - Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - }
10/10/2022 COT - FCON - Sprinkler - Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - }
10/10/2022 COT - FCON - Fire - Final Passed {Activity date: 10/10/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - }
10/11/2022 COT - LCBU - Building Final Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/11/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/22/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA. MRI room} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
All rooms except MRI & Control rooms}
10/11/2022 COT - LCME - Mechanical Final Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/11/2022 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/13/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
OK to drop ceiling tiles in all area except x-ray room} ; {Activity date: 09/12/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA} ; {Activity date: 08/02/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA MRI room only}
10/11/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - PA
Chilled water loop ok to insulate.} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
All rooms except MRI & Control rooms}
10/11/2022 COT - LCEL - Electrical Final Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 10/07/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - PA}
10/11/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/11/2022 COT - LCPL - Plumbing Final Passed {Activity date: 10/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}