Permit: T21CM09170
Permit Details
Apply Date:
11/24/2021
Applicant:
Technicians for Sustainability
Description:
roof mount 9.60 kW photovoltaic solar system; 24 modules, 2 branches, PV subpanel, 40A PV breaker on 200A bus with 200A MCB
Contractors:
- Technicians for Sustainability
Permit Reviews
Permit Number - T21CM09170
Permit Status: Final
Permit Description: roof mount 9.60 kW photovoltaic solar system; 24 modules, 2 branches, PV subpanel, 40A PV breaker on 200A bus with 200A MCB
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/24/2021 | OTHER | 12/23/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM09170
Permit Description: roof mount 9.60 kW photovoltaic solar system; 24 modules, 2 branches, PV subpanel, 40A PV breaker on 200A bus with 200A MCB
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/31/2022 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE DGC |
| 03/31/2022 | ELECTRIC - FINAL | TGAUSP | Approved | Approved, please send DGC Clearance to TEP for the solar meter |
| 03/31/2022 | BUILDING - FINAL | TGAUSP | Approved | Approved |