Permit: T21CM09167
Permit Details
Apply Date:
11/24/2021
Applicant:
Technicians for Sustainability
Description:
roof mount 5.20 kW photovoltaic solar system; 13 modules, 2 branches, PV subpanel, 30A PV breaker, line side interconnection
Contractors:
- Technicians for Sustainability
Permit Reviews
Permit Number - T21CM09167
Permit Status: Final
Permit Description: roof mount 5.20 kW photovoltaic solar system; 13 modules, 2 branches, PV subpanel, 30A PV breaker, line side interconnection
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/15/2022 | REVISION - - 1ST | 01/19/2022 | COMPLETED |
03/09/2022 | REVISION - - 2ND | 03/23/2022 | COMPLETED |
11/24/2021 | OTHER | 12/16/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM09167
Permit Description: roof mount 5.20 kW photovoltaic solar system; 13 modules, 2 branches, PV subpanel, 30A PV breaker, line side interconnection
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/29/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE DGC |
03/29/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap Clear dgc Close permit |