Permit: T21CM09123
Permit Details
Status:
Final
Type:
SOLAR WAIVER - RES
Address:
9350 E SPEEDWAY BL #27
Address NEW:
9350 E SPEEDWAY BL #27
Apply Date:
11/23/2021
Applicant:
Sunrun Installation Services, Inc
Description:
- SYSTEM SIZE: 9100W DC, 6240W AC- MODULES: (26) HANWHA Q-CELLS: Q.PEAK DUO-G8+ 350- INVERTERS: (26) ENPHASE ENERGY: IQ7-60-2-US- RACKING: ; SOLLEGA FASTRACK510 WITH 304 STAINLESS STEEL HARDWARE NEW 100AMP SUB-PANEL TO BE INSTALLED.
Architects:
- Same as above
Contractors:
- Sunrun Installation Services, Inc
Permit Reviews
Permit Number - T21CM09123
Permit Status: Final
Permit Description: - SYSTEM SIZE: 9100W DC, 6240W AC- MODULES: (26) HANWHA Q-CELLS: Q.PEAK DUO-G8+ 350- INVERTERS: (26) ENPHASE ENERGY: IQ7-60-2-US- RACKING: ; SOLLEGA FASTRACK510 WITH 304 STAINLESS
STEEL HARDWARE
NEW 100AMP SUB-PANEL TO BE INSTALLED.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/27/2022 | RESUBMITTAL | 01/31/2022 | COMPLETED |
| 11/23/2021 | OTHER | 12/17/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM09123
Permit Description: - SYSTEM SIZE: 9100W DC, 6240W AC- MODULES: (26) HANWHA Q-CELLS: Q.PEAK DUO-G8+ 350- INVERTERS: (26) ENPHASE ENERGY: IQ7-60-2-US- RACKING: ; SOLLEGA FASTRACK510 WITH 304 STAINLESS
STEEL HARDWARE
NEW 100AMP SUB-PANEL TO BE INSTALLED.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/31/2022 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE DGC |
| 05/31/2022 | ELECTRIC - FINAL | RCHANDLER | Approved | AP. DGC clearance for TEP. |
| 05/31/2022 | BUILDING - FINAL | RCHANDLER | Approved | AP |