Permit: T21CM09070
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
10050 E 5TH ST
Address NEW:
10050 E 5TH ST
Apply Date:
11/20/2021
Applicant:
Description:
SFR T772DEAC T21-M0017
Outstanding Activity Conditions
Permit Number - T21CM09070
Permit Status: Issued
Permit Description: SFR T772DEAC T21-M0017
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 11/20/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 11/20/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
| 11/20/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM09070
Permit Description: SFR T772DEAC T21-M0017
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 01/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 01/06/2022 | COT - RSPL - Sewer | Passed | {Activity date: 01/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 01/06/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 01/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 01/13/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 01/13/2022 | COT - RSBU - Preslab | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 01/13/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 01/13/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 02/01/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 02/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 02/18/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/18/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/11/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by VVERA1 - DE some corrected, more remain. Field 10-12 Sent text at 9:20} ; {Activity date: 02/01/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by VVERA1 - DE. Block edges of heeting turned the wrong way.} |
|
| 03/10/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 03/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE ECO} | |
| 03/10/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 03/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP. ECO clearance for TEP. Field 10-12 CONTACTS: RICHMOND AMERICAN HOMES ** APA *** - 520-229-5432 , CONTRACTOR: RICHMOND AMERICAN HOMES ** APA *** (520-904-5039- 520-229-5441), No Other Contact listed} |
|
| 05/24/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 05/24/2022 | COT - LCBU - Framing | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 05/24/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 05/24/2022 | RSME - Mechanical Progress | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 05/24/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 06/22/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/20/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA per text from contractor } |
|
| 08/08/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 08/08/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CODE} | |
| 08/17/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} | |
| 08/17/2022 | RSBU - Building Final | Passed | {Activity date: 08/17/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS } ; {Activity date: 08/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} |
|
| 08/17/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} | |
| 08/17/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/08/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -Partial Approval-SWG clearance.} | |
| 08/17/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} |