Permit: T21CM08865
Permit Details
Apply Date:
11/12/2021
Applicant:
Description:
New 4,846 sf building and parking lot
Permit Reviews
Permit Number - T21CM08865
Permit Status: Complete
Permit Description: New 4,846 sf building and parking lot
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/06/2022 | RESUBMITTAL | 07/13/2022 | COMPLETED |
08/16/2022 | REVISION - - 1ST | 08/29/2022 | COMPLETED |
09/13/2022 | REVISION - - 2ND | 10/04/2022 | COMPLETED |
09/27/2022 | REVISION - - 3RD | 10/04/2022 | COMPLETED |
11/12/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 01/31/2022 | COMPLETED |
06/06/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/07/2023 | APPROVED |
Conditions
Permit Number - T21CM08865
Permit Status: Complete
Permit Description: New 4,846 sf building and parking lot
Date | Description | Comments |
---|---|---|
11/29/2021 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
11/29/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
11/29/2021 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
11/29/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
11/29/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
07/13/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
11/29/2021 | SHOP DRAWINGS REQUIRED FOR ROOF JOISTS | |
07/13/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM08865
Permite Description: New 4,846 sf building and parking lot
Total Outstanding Inspections - 14
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
11/23/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
02/15/2023 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Applicable | N/A |
02/15/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | N/A |
11/09/2022 | COT - HCBU - Building Progress | N/A | Partial Pass | 5th lift at Lobby and Oil Room. |
12/13/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
03/27/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
02/02/2023 | COT - LCEL - Electrical Underground | N/A | Partial Pass | Feeders for service. |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
06/07/2023 | COT - LCPL - Backwater Valve | N/A | Not Applicable | |
06/07/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
06/07/2023 | COT - LCBU - Building Final | N/A | Partial Pass | 6/7/23: OK to issue TCO Level 4, pending final approval of Site Engineering. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM08865
Permit Description: New 4,846 sf building and parking lot
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/28/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/22/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 09/15/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 09/13/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Partial Approval: Observed compaction below footings.} | |
12/13/2022 | COT - LCPL - Rough Soil | Passed | ||
02/15/2023 | COT - HCBU - Building Progress | Passed | ||
02/15/2023 | COT - LCBU - Roof Nailing | Passed | ||
02/15/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/07/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
03/07/2023 | COT - LCBU - Framing | Passed | ||
03/07/2023 | COT - LCEL - Electrical Progress | Passed | ||
03/17/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
03/27/2023 | BULD - Electrical Clearance | Passed | ||
04/04/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
04/04/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
04/04/2023 | COT - LCME - Mechanical Progress | Passed | ||
06/05/2023 | COT - FCON - Fire - Final | Passed | ||
06/07/2023 | COT - LCBU - Preslab | Passed | ||
06/07/2023 | COT - LCEL - Electrical Underground | Passed | ||
06/07/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
06/07/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
06/07/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
06/07/2023 | COT - LCPL - Plumbing Final | Passed | ||
06/07/2023 | COT - HCBU - Masonry Pregrout | Passed | ||
06/07/2023 | COT - LCPL - Sewer | Passed | ||
06/07/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
06/07/2023 | COT - LCEL - Electrical Final | Passed | ||
06/07/2023 | COT - LCME - Mechanical Final | Passed | ||
06/12/2023 | COT - LCBU - Building Final | Passed |