Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM08828
Permit Details
Apply Date:
11/10/2021
Applicant:
Description:
Multiple single story drive up and walk up unconditioned storage buildings, to include site work and
Permit Reviews
Permit Number - T21CM08828
Permit Status: Complete
Permit Description: Multiple single story drive up and walk up unconditioned storage buildings, to include site work and
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/25/2022 | RESUBMITTAL | 04/15/2022 | COMPLETED |
| 05/12/2022 | RESUBMITTAL | 05/24/2022 | COMPLETED |
| 05/26/2022 | RESUBMITTAL | 06/01/2022 | COMPLETED |
| 11/10/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 01/31/2022 | COMPLETED |
| 04/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/20/2023 | APPROVED |
Conditions
Permit Number - T21CM08828
Permit Status: Complete
Permit Description: Multiple single story drive up and walk up unconditioned storage buildings, to include site work and
| Date | Description | Comments |
|---|---|---|
| 05/19/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 05/19/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM08828
Permite Description: Multiple single story drive up and walk up unconditioned storage buildings, to include site work and
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
| 01/10/2023 | COT - LCBU - Building Progress | N/A | Partial Pass | partial approval for 1 light pole base, ok to place concrete |
| 10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
| 03/15/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Knox key switch for entry gate, fire extinguishers |
| 04/20/2023 | ENGR Engineering Final | N/A | Requested |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM08828
Permit Description: Multiple single story drive up and walk up unconditioned storage buildings, to include site work and
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/01/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, breezeways ok for concrete placement. } ; {Activity date: 06/29/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for 6 pads at Building B} ; {Activity date: 06/27/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, building B storage foundations & column footings ok for concrete placement.} ; {Activity date: 06/10/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Footing and slab for building A. } |
|
| 08/18/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/18/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved Building A and C. Partial in building B. Okay to put roof panels from east side of entry to the firewall in center of building. } ; {Activity date: 08/15/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Building A missing red head bolts to attach to masonry wall. Missing screws on interior sheathing. Check every stud for missing screws. Building B Not ready} ; {Activity date: 08/11/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Contractor cancelled} ; {Activity date: 07/29/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready. Building A. Studs missing. Along with a couple of screws in studs. } ; {Activity date: 06/27/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Building A ok to Sheetrock.} |
|
| 08/18/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 08/18/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved. Building A and C. Not ready on building B.} ; {Activity date: 07/29/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Building C only.} ; {Activity date: 07/22/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Building C approved.} | |
| 09/02/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/01/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 08/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Partial on Building A. Fill in gaps in sheathing. Partial on building B. Partial on building C. Need to fasten loose panels. } ; {Activity date: 08/15/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Building B Not ready.} ; {Activity date: 08/11/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Contractor cancelled} ; {Activity date: 07/22/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Building C approved.} ; {Activity date: 06/22/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, west building sill plate attachments ok to proceed.} |
|
| 10/12/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, verified 3 layers to deck at the center demising wall of Bldg B } ; {Activity date: 09/09/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready 3 layers of drywall do not go to the top deck} ; {Activity date: 09/08/2022; Status: Partial Approval; Inspector: TGAUPS; Comment: Entered by RSALDAT1 - Approved NW 1-Hour wall at Building C NOTE: MORE INSPECTONS NECESSARY DUE TO MULTI BUILDING.} |
|
| 11/09/2022 | COT - LCBU - Preslab | Passed | ||
| 01/13/2023 | BULD - Electrical Clearance | Passed | ||
| 01/30/2023 | COT - LCEL - Service Upgrade | Passed | Approved, ECO Clearance sent | |
| 03/15/2023 | COT - LCEL - Electrical Final | Passed | Electrical panel,meter, conduit, and light fixtures are installed and properly working. | |
| 03/15/2023 | COT - LCBU - Building Final | Passed | Storage facility is completed. Okay to issue a Level 4 Certificate of Occupancy for this permit. | |
| 03/15/2023 | COT - LCBU - Building Progress | Passed | Project is in punch list mode with paint touch-up and clean-up. | |
| 03/15/2023 | COT - LCBU - Building Above Ceiling | Passed | There are no ceilings in the storage units. | |
| 03/15/2023 | COT - LCEL - Electrical Above Ceiling | Passed | There are no ceilings in the storage units. | |
| 03/15/2023 | COT - LCEL - Electrical Progress | Passed | All exterior and interior lights are installed and operational. | |
| 03/15/2023 | COT - LCBU - Masonry Pregrout | Passed | Demising wall is complete and fully grouted. | |
| 03/15/2023 | COT - LCEL - Electrical Intermediate | Passed | All exterior and interior lights are installed and operational. | |
| 04/04/2023 | COT - FCON - Fire - Final | Passed | ||
| 04/05/2023 | COT - LCEL - Outdoor Lighting | Passed |