Permit Reviews

Permit Number - T21CM08813
Permit Status: Complete
Permit Description: SFR UNIT 1
Start Date Submittal Complete Date Status  
01/14/2022 RESUBMITTAL 02/07/2022 COMPLETED Review Details
10/13/2022 REVISION - - 1ST 10/19/2022 ACTIVE Review Details
11/10/2021 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 12/08/2021 COMPLETED Review Details
12/29/2021 RESUBMITTAL 01/14/2022 COMPLETED Review Details
10/28/2022 RESIDENTIAL NEW DWELLING v.1 11/01/2022 REQUIRES RESUBMIT Review Details
01/04/2023 RESIDENTIAL NEW DWELLING v.1 03/21/2023 APPROVED Review Details

Conditions

Permit Number - T21CM08813
Permit Status: Complete
Permit Description: SFR UNIT 1
Date Description Comments
11/23/2021 SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927.
11/23/2021 SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927.
11/23/2021 FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927.
11/23/2021 FUP T21OT00862 MUST BE PAID BEFORE FINAL INSPECTIONS.
11/23/2021 FUP T21OT00862 MUST BE PAID BEFORE FINAL INSPECTIONS.
09/06/2023 This project is within a floodplain and requires an elevation certificate. Submission and Issuance of a Floodplain Use Permit (FUP) is required PRIOR TO ISSUANCE of this permit. An intermediate Elevation Certificate is required PRIOR TO GRADING and/or PRE-SLAB INSPECTION. Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit.
03/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM08813
Permite Description: SFR UNIT 1
Total Outstanding Inspections - 4

Completed Inspections

Permit Status: Complete
Permit Number: T21CM08813
Permit Description: SFR UNIT 1
Total Completed Inspections - 22
Date Description Inspector Results Comments
04/28/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 04/28/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
04/28/2022 COT - RSEL - Electrical Underground Passed {Activity date: 04/28/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
12/22/2022 COT - RSEL - Construction Power Passed
12/22/2022 COT - RSEL - Temporary Service Passed
12/22/2022 COT - LCBU - Framing Passed
12/22/2022 RSME - Mechanical Progress Passed
12/22/2022 COT - LCPL - Plumbing Intermediate Passed
12/22/2022 COT - RSPL - Yard Water Line Passed
02/22/2023 BULD - Electrical Clearance Passed TEP ECO
04/18/2023 COT - RSBU - Excavation/Rebar/Zoning Passed Approved for both porches on A and B. (1 and 2) Okay for concrete placement. 4/18/2023
09/11/2023 COT - RSBU - Preslab Passed
09/11/2023 COT - RSPL - Rough Soil Passed
09/11/2023 COT - RSPL - Plumbing Final Passed Plumbing fixtures are installed and operational.
09/11/2023 COT - RSEL - Electrical Final Passed Electrical panel is properly labeled, all electrical fixtures are installed and operational. Kitchen, garage, bathroom, and exterior outlets are GFCI protected. Bedrooms are AFCI protected.
09/11/2023 COT - RSME - Mechanical Final Passed A/C unit is installed and operational. Registers are installed.
09/11/2023 RSBU - Building Final Passed Construction is complete. Okay to issue Certificate of Occupancy for 2528 N Fair Oaks Avenue #1.
09/11/2023 COT - RSPL - Sewer Passed
04/29/2024 ENGR Engineering Final Passed porches present no construction/equipment observed.
05/22/2024 COT - RSBU - Roof Nailing Passed
05/22/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/22/2024 COT - RSEL - Outdoor Lighting Passed
05/22/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
2022-10-12 - UPDATE TO T21CM008813 _ T21CM08814_V1.PDF DOCUMENTS VIEW
CONS-CONS-2- PORCH-2528-FAIR OAKS_V1.PDF DOCUMENTS VIEW