Permit: T21CM08666
Permit Details
Apply Date:
11/04/2021
Applicant:
Technicians for Sustainability
Description:
roof mount 5.63 kW photovoltaic solar system; 15 modules, 2 branches, PV subpanel, 30A PV breaker on 125A bus with 100A MCB [new load center]
Contractors:
- Technicians for Sustainability
Completed Inspections
Permit Status: Final
Permit Number: T21CM08666
Permit Description: roof mount 5.63 kW photovoltaic solar system; 15 modules, 2 branches, PV subpanel, 30A PV breaker on 125A bus with 100A MCB [new load center]
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/07/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE DGC |
| 12/07/2021 | BUILDING - FINAL | DQUINN | Approved | Ap Clear dgc Close permit |
| 12/07/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap Clear dgc Close permit |