Permit: T21CM08532
Permit Details
Apply Date:
10/29/2021
Applicant:
Dana Petty
Description:
SFR MERI258019 T19-M0161
Conditions
Permit Number - T21CM08532
Permit Status: Issued
Permit Description: SFR MERI258019 T19-M0161
Date | Description | Comments |
---|---|---|
10/29/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
10/29/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
10/29/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM08532
Permite Description: SFR MERI258019 T19-M0161
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/25/2022 | COT - LCBU - Framing | N/A | Not Ready | NOT READY PER PREVIOUS COMMENTS. |
10/25/2022 | COT - LCPL - Plumbing Intermediate | N/A | Re-inspection required | |
10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM08532
Permit Description: SFR MERI258019 T19-M0161
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/07/2022 | COT - RSPL - Sewer | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
07/07/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/05/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE. Support underground with dirt} | |
07/15/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
07/15/2022 | COT - RSBU - Preslab | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
07/15/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 07/07/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} ; {Activity date: 07/05/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} | |
07/15/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
07/15/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
08/09/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/09/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
11/23/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
02/09/2023 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
02/09/2023 | COT - RSPL - Plumbing Final | Passed | ||
02/09/2023 | COT - RSEL - Electrical Final | Passed | ||
02/09/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
02/09/2023 | COT - RSME - Mechanical Final | Passed | ||
02/09/2023 | RSBU - Building Final | Passed |