Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
10/29/2021
Applicant:
Description:
Tenant finish

Permit Reviews

Permit Number - T21CM08514
Permit Status: Complete
Permit Description: Tenant finish
Start Date Submittal Complete Date Status  
10/29/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 12/06/2021 COMPLETED Review Details
12/18/2021 RESUBMITTAL 12/27/2021 COMPLETED Review Details
02/15/2023 COMMERCIAL REVIEW - FULL v.1 03/13/2023 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM08514
Permite Description: Tenant finish
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
03/28/2023 COT - FCON - Fire - Final N/A Partial Pass Ok for Level 4 TCO
Need Knox FDC Caps
Need Front Door Exit sign repaired

Completed Inspections

Permit Status: Complete
Permit Number: T21CM08514
Permit Description: Tenant finish
Total Completed Inspections - 22
Date Description Inspector Results Comments
11/08/2022 COT - LCEL - Electrical Progress Passed
11/08/2022 COT - LCPL - Plumbing Progress Passed Rough soil for restrooms and break room, okay for concrete placement
11/21/2022 COT - LCEL - Electrical Intermediate Passed Approved at all walls
11/21/2022 COT - LCPL - Plumbing Intermediate Passed Approved at all walls
11/21/2022 COT - LCBU - Preslab Passed
11/21/2022 COT - LCBU - Framing Passed
12/02/2022 COT - HCBU - Interior Shear Bracing Passed
02/08/2023 COT - LCBU - Building Progress Passed screw inspection on fitting rooms
03/17/2023 COT - LCPL - Plumbing Final Passed Plumbing for restrooms, mop sink, and break room is complete and operational.
03/17/2023 COT - LCPL - Plumbing Above Ceiling Passed Plumbing for restrooms, mop sink, and break room is complete and operational.
03/17/2023 COT - LCME - Mechanical Intermediate Passed All equipment is installed and operational. Okay to install ceiling tiles throughout building.
03/27/2023 COT - LCME - Mechanical Progress Passed All mechanical equipment and ductwork is installed and fully functional.
03/27/2023 COT - LCEL - Electrical Final Passed Electrical panels are properly labeled and panel schedules are inside door.
03/27/2023 COT - LCME - Mechanical Above Ceiling Passed All mechanical equipment and ductwork is installed and fully functional.
03/27/2023 COT - LCBU - Building Above Ceiling Passed
03/27/2023 COT - LCEL - Electrical Above Ceiling Passed All electrical conduit and boxes are properly installed and marked.
03/27/2023 COT - LCME - Mechanical Final Passed Mechanical equipment, ductwork, and thermostats are complete and operational.
03/28/2023 COT - FCON - Alarm - Final Passed
03/28/2023 COT - FCON - Sprinkler - Final Passed
03/29/2023 COT - HCBU - CofO Passed
03/29/2023 COT - LCBU - Building Final Passed ready for C/O
04/03/2023 COT - FCON - Fire - Final Passed