Permit Reviews
Permit Number - T21CM08494
Permit Status: Inspections
Permit Description: Addition to Existing Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/12/2022 | REVISION - - 1ST | 10/13/2022 | ACTIVE |
| 10/28/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 12/01/2021 | COMPLETED |
| 12/16/2021 | RESUBMITTAL | 01/11/2022 | COMPLETED |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/16/2022 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM08494
Permit Status: Inspections
Permit Description: Addition to Existing Building
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 04/12/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 04/12/2024 | Shop Drawings required for sprinklers |
| 04/12/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 04/12/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T21CM08494
Permite Description: Addition to Existing Building
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - FCON - Underground Flush | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
| 10/26/2022 | FCON – OH Piping & Hydro | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Underground Pressure | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Backwater Valve | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
| 03/03/2023 | COT - LCEL - Electrical Underground | N/A | Not Applicable | overhead service |
| 09/14/2023 | COT - LCPL - Plumbing Final | N/A | Partial Pass | Partial, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health approvals (Note completion of walk in, roof drains, condensate at sidewalk) |
| 03/26/2024 | PDSD Building Division - Unspecified Remote Video | N/A | Canceled | |
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
| 09/14/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Partial, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health approvals (Note completion of walk in, roof drains, condensate at sidewalk) |
Completed Inspections
Permit Status: Inspections
Permit Number: T21CM08494
Permit Description: Addition to Existing Building
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/17/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 12/12/2022 | COT - LCBU - Masonry Pregrout | Passed | Approved top of walls, okay to grout | |
| 12/20/2022 | COT - LCBU - Framing | Passed | Ok to insulate and cover walls. | |
| 03/03/2023 | COT - LCME - Mechanical Intermediate | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 03/03/2023 | COT - LCEL - Electrical Progress | Passed | ||
| 03/03/2023 | COT - LCPL - Plumbing Progress | Passed | ||
| 03/03/2023 | COT - LCEL - Electrical Intermediate | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
| 03/03/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCBU - Building Above Ceiling | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCEL - Electrical Above Ceiling | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCBU - Building Progress | Passed | ||
| 03/03/2023 | COT - LCPL - Plumbing Intermediate | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCBU - Roof Nailing | Passed | ||
| 03/03/2023 | COT - LCME - Mechanical Above Ceiling | Passed | Approved, okay to insulate and cover | |
| 03/03/2023 | COT - LCBU - Preslab | Passed | ||
| 03/27/2023 | COT - LCPL - Sewer | Passed | Approved connection of 100/200 GPM grease interceptor and sewer connection to existing clay pipe main line, okay to backfill and shade | |
| 07/06/2023 | BULD - Electrical Clearance | Passed | Approved 400A service upgrade, INCR Clearance to TEP is required for the cutover | |
| 07/06/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
| 09/14/2023 | COT - LCME - Mechanical Final | Passed | Approved, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health | |
| 09/14/2023 | COT - LCEL - Electrical Final | Passed | Approved, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health | |
| 04/09/2024 | ENGR Engineering Final | Passed |