Permit Details

Status:
Inspections
Type:
Commercial Building
Address:
4420 S 6TH AV
Address NEW:
4420 S 6TH AV
Apply Date:
10/28/2021
Applicant:
FERNANDO CAMACHO
Description:
Addition to Existing Building

Permit Reviews

Permit Number - T21CM08494
Permit Status: Inspections
Permit Description: Addition to Existing Building
Start Date Submittal Complete Date Status  
10/12/2022 REVISION - - 1ST 10/13/2022 ACTIVE Review Details
10/28/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 12/01/2021 COMPLETED Review Details
12/16/2021 RESUBMITTAL 01/11/2022 COMPLETED Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 11/16/2022 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T21CM08494
Permit Status: Inspections
Permit Description: Addition to Existing Building
Total Outstanding Activity Conditions - 4
Date Name
04/12/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/12/2024 Shop Drawings required for sprinklers
04/12/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/12/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections
Permit Number: T21CM08494
Permite Description: Addition to Existing Building
Total Outstanding Inspections - 14
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - FCON - Underground Flush N/A Not Ready
10/26/2022 COT - LCEL - Outdoor Lighting N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/26/2022 COT - FCON - Sprinkler - Final N/A Not Ready
10/26/2022 FCON – OH Piping & Hydro N/A Not Ready
10/26/2022 COT - FCON - Underground Pressure N/A Not Ready
10/26/2022 COT - LCPL - Backwater Valve N/A Not Ready
10/26/2022 COT - LCPL - Rough Soil N/A Not Ready
10/26/2022 COT - LCBU - Masonry Pregrout N/A Not Ready
03/03/2023 COT - LCEL - Electrical Underground N/A Not Applicable overhead service
09/14/2023 COT - LCPL - Plumbing Final N/A Partial Pass Partial, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health approvals
(Note completion of walk in, roof drains, condensate at sidewalk)
03/26/2024 PDSD Building Division - Unspecified Remote Video N/A Canceled
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
09/14/2023 COT - LCBU - Building Final N/A Partial Pass Partial, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health approvals
(Note completion of walk in, roof drains, condensate at sidewalk)

Completed Inspections

Permit Status: Inspections
Permit Number: T21CM08494
Permit Description: Addition to Existing Building
Total Completed Inspections - 23
Date Description Inspector Results Comments
10/17/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
12/12/2022 COT - LCBU - Masonry Pregrout Passed Approved top of walls, okay to grout
12/20/2022 COT - LCBU - Framing Passed Ok to insulate and cover walls.
03/03/2023 COT - LCME - Mechanical Intermediate Passed Approved, okay to insulate and cover
03/03/2023 COT - LCME - Mechanical Progress Passed
03/03/2023 COT - LCEL - Electrical Progress Passed
03/03/2023 COT - LCPL - Plumbing Progress Passed
03/03/2023 COT - LCEL - Electrical Intermediate Passed Approved, okay to insulate and cover
03/03/2023 COT - LCPL - Plumbing Roof Drains Passed
03/03/2023 COT - LCPL - Plumbing Above Ceiling Passed Approved, okay to insulate and cover
03/03/2023 COT - LCBU - Building Above Ceiling Passed Approved, okay to insulate and cover
03/03/2023 COT - LCEL - Electrical Above Ceiling Passed Approved, okay to insulate and cover
03/03/2023 COT - LCBU - Building Progress Passed
03/03/2023 COT - LCPL - Plumbing Intermediate Passed Approved, okay to insulate and cover
03/03/2023 COT - LCBU - Roof Nailing Passed
03/03/2023 COT - LCME - Mechanical Above Ceiling Passed Approved, okay to insulate and cover
03/03/2023 COT - LCBU - Preslab Passed
03/27/2023 COT - LCPL - Sewer Passed Approved connection of 100/200 GPM grease interceptor and sewer connection to existing clay pipe main line, okay to backfill and shade
07/06/2023 BULD - Electrical Clearance Passed Approved 400A service upgrade, INCR Clearance to TEP is required for the cutover
07/06/2023 COT - HCEL - Grounding/Bonding Passed
09/14/2023 COT - LCME - Mechanical Final Passed Approved, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health
09/14/2023 COT - LCEL - Electrical Final Passed Approved, recommendation for level 2 TCO, employees only for equipment testing, staff training and stocking. Pending Engineering, and Health
04/09/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2022-10-11 - UPDATE TO T21CM08494_V1.PDF DOCUMENTS VIEW
REV1_LETTER_V1.PDF DOCUMENTS VIEW
CONS-T21CM08494 APPROVED STAMPED_REV1_PLAN_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
FIRE HOSE EXTENSION MAP.PDF CONSTRPLANS VIEW
COT WATER FLOW LETTER.PDF DOCUMENTS VIEW
CC CODEREVIEWCHECKLIST.PDF DOCUMENTS VIEW
MECH CHECK.PDF DOCUMENTS VIEW
NW COT WATER MAP.PDF CONSTRPLANS VIEW
NE COT WATER MAP.PDF CONSTRPLANS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SYSTEMS DESIGN REPORT.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW