Permit: T21CM08364
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
11713 S OLD NOGALES HY
Address NEW:
11713 S OLD NOGALES HY
Apply Date:
10/25/2021
Applicant:
George Herman
Description:
Equip new well, control building, and perimeter fence.
Permit Reviews
Permit Number - T21CM08364
Permit Status: Issued
Permit Description: Equip new well, control building, and perimeter fence.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/25/2021 | OTHER | 11/18/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM08364
Permit Status: Issued
Permit Description: Equip new well, control building, and perimeter fence.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 11/04/2021 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 11/04/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
| 11/04/2021 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 11/04/2021 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 11/04/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 11/04/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM08364
Permite Description: Equip new well, control building, and perimeter fence.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2022 | COT - LCBU - Framing | N/A | Canceled | {Activity date: 09/16/2022; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by VVERA1 - NA} |
| 05/29/2024 | COT - LCEL - Service Upgrade | N/A | Not Applicable | |
| 05/29/2024 | COT - LCEL - Temporary Service | N/A | Not Applicable | |
| 05/29/2024 | COT - LCEL - Construction Power | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM08364
Permit Description: Equip new well, control building, and perimeter fence.
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/29/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 04/29/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 04/29/2022 | COT - LCBU - Preslab | Passed | {Activity date: 04/29/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 04/29/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 04/29/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 07/27/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap All trenches complete for backfilling} ; {Activity date: 04/26/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, conduit sweeps and raceways installed under control building heading towards well heads. Ok to backfill progress areas.} |
|
| 09/16/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 09/16/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO} | |
| 09/16/2022 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. Top-out at 8 feet 8 inches.} ; {Activity date: 05/05/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, first lift for control Building CMU ok to grout and proceed.} | |
| 05/29/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 05/29/2024 | COT - LCBU - Building Progress | Passed | ||
| 05/29/2024 | COT - LCBU - Building Final | Passed | ||
| 05/29/2024 | COT - LCEL - Electrical Final | Passed | ||
| 05/29/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
| 05/29/2024 | COT - LCME - Mechanical Final | Passed |