Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
10/22/2021
Applicant:
a23 Studios
Description:
OFFICE
Architects:
  • Burak Bekat (a23 Studios)
Contractors:
  • G&J Development, Inc. (Garret Cunningham)

Permit Reviews

Permit Number - T21CM08332
Permit Status: C of o
Permit Description: OFFICE
Start Date Submittal Complete Date Status  
10/22/2021 COMMERCIAL - TI 11/18/2021 COMPLETED Review Details
11/26/2021 RESUBMITTAL 12/10/2021 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T21CM08332
Permit Description: OFFICE
Total Completed Inspections - 15
Date Description Inspector Results Comments
12/14/2021 BUILDING - FINAL JBURGE Approved Approved. Pending Fire Final
12/14/2021 FRAMING JBURGE Approved Approved
12/14/2021 BUILDING ABOVE CEILING JBURGE Approved Approved
12/14/2021 BUILDING - PROGRESS JBURGE Approved Approved
12/14/2021 ELECTRIC - INTERMEDIATE JBURGE Approved Approved
12/14/2021 ELECTRIC - ABOVE CEILING JBURGE Approved Approved
12/14/2021 ELECTRIC - FINAL JBURGE Approved Approved
12/14/2021 PLUMBING - ROUGH, SOIL JBURGE Approved Approved
12/14/2021 PLUMBING - INTERMEDIATE JBURGE Approved Approved
12/14/2021 PLUMBING - FINAL JBURGE Approved Approved
12/14/2021 MECHANICAL - ABOVE CEILING JBURGE Approved Approved
12/14/2021 MECHANICAL - FINAL JBURGE Approved Approved
02/01/2022 FIRE - FINAL wmotto Approved fordney approved these on the FC permit
02/01/2022 FIRE - ALARM FINAL wmotto Approved fordney approved these on the FC permit
02/01/2022 FIRE SPKLR - FINAL wmotto Approved fordney approved these on the FC permit