Permit: T21CM08324
Permit Details
Apply Date:
10/21/2021
Applicant:
Solon Corporation
Description:
223.08 kW - DC Solar Canopy Project
Contractors:
- Solon Corporation
Permit Reviews
Permit Number - T21CM08324
Permit Status: L of c
Permit Description: 223.08 kW - DC Solar Canopy Project
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/21/2021 | COMMERCIAL - TI | 11/22/2021 | COMPLETED |
| 12/27/2021 | RESUBMITTAL | 01/28/2022 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T21CM08324
Permit Description: 223.08 kW - DC Solar Canopy Project
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2022 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved, okay to pour |
| 03/25/2022 | ELECTRIC - OUTDOOR LIGHTING | TGAUSP | Approved | Approved, in place |
| 03/25/2022 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | NA |
| 03/25/2022 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | Approved |
| 03/25/2022 | FRAMING | TGAUSP | Approved | Approved for canopies A and B |
| 05/23/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved, okay to backfill the progress areas |
| 05/23/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | Approved |
| 05/23/2022 | BUILDING - PROGRESS | TGAUSP | Approved | Approved |
| 06/04/2022 | BUILDING - FINAL | DMUNIZ1 | Approved | |
| 06/04/2022 | ELECTRIC - FINAL | DMUNIZ1 | Approved | INSPECTION OF LINE SIDE TAP FOR INTERCONNECTION OF 650AMP PV DISCONNECT, TO 1200AMP SES. VERBAL CLEARANCE SENT TO TEP RECN/DGL. |
| 06/08/2022 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE DGC |